OR 99E at Airport Road

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Albany, Linn)


​​​​​Install a left turn lane on the northbound Airport Road approach at the signalized intersection with OR 99E.


Construction banner

Impacts

Traffic Impact

Online Open House

Expect lane closures and delays.


Construction Impacts

Expect construction noise and lane closures.
Work will be done nightly Sunday through Thursday from 7 p.m. to 6 a.m. 

Construction Activities

​Our contractor will b​egin work on installing all underground electrical lines and foundations for new signal at Airport Road and OR 99E. 

Meetings and Events

​Find out what road work is being done in 2022!

Visit our construction online open house to learn about the projects and the impacts to traffic that may occur as we work to build, repair and improve the roads that connect the communities of Region 2.

Sign up to receive future information about projects, road closures or invites to events. You can browse the different topics and sign up for the ones that interest you!

Details

About

​This All Roads Transportation Safety project is in an area that has a higher than normal crash rate (in both frequency and severity), as identified by the Safety Priority Index System.​

In order to improve the intersection, this project will:

  • Re-align Airport Road and install a left turn lane.
  • Add curb and sidewalk along Airport Road.
  • Upgrade ADA ramps at the OR 99E/Aiport Road intersection.
  • Replace and upgrade intersection traffic signals. 

Schedule​

Design complete: Fall 2021

Construction: Spring-Summer 2022

Location

OR 99E |

​at milepost 0.4​

Cost and Funding

​Design and construction: $1,860,000

Contacts & Media

Project area map

Project Contacts

Transportation Project Manager
Paul Welch
Email
paul.welch@odot.oregon.gov
Phone
503-986-2702

Public Information Officer
Angela Beers Seydel
Email
angela.beers-seydel@odot.oregon.gov
Phone
541-726-2442

Last Updated

7/18/2022 9:44 AM

Project Number

20183