Mission Street: 17th Street to I-5 North Ramps

Design Phase

Region 2: Willamette Valley and Northwest Oregon (Salem, Marion)


​Adding new traffic light systems to improve the flow of traffic.

OOH banner

Details

About

Enlarged project mapOpen House IconMission Street has seven signalized intersections that are historical high crash locations for Region 2. Most of the crashes are due to congestion. Our goal with this project is to reduce some congestion by using newer signal timing technology.

In order to improve the flow of traffic on Mission Street, we will replace any damaged traffic signal sensors, as well as install:  

  • New traffic controllers.

  • Traffic detectors.

  • Technology that works with traffic conditions and signals to keep traffic moving smoothly.

This technology will adjust when a green light starts and ends to follow the current traffic pattern. This will benefit these intersections because it will help reduce congestion and fuel consumption, automatically adapt to unexpected changes in traffic conditions and improve travel time reliability.​

The installation of the new equipment will occur at night and should have minimal impacts to traffic flow. If lane closures are needed, the work zone will be controlled by flaggers.

Schedule

Design: 2019-2021

Construction: 2022

Location

OR 22 | ​Between I-5 and 17th Street SE

Cost and Funding

​​Design and Construction: $1,468,000

​Pedestrians, including those with disabilities, will have access through or around work zones. 

Contacts & Media

Project area map

Project Contacts

Transportation Project Manager
Paul Welch
Email
paul.welch@odot.state.or.us
Phone
503-986-2702

Public Information Officer
Lou Torres
Email
louis.c.torres@odot.state.or.us
Phone
503-986-2880

Last Updated

5/6/2021 10:24 PM

Project Number

20214



Your browser is out-of-date! It has known security flaws and may not display all features of this and other websites. Learn how

×