Wallowa and Lostine Curb Ramp Upgrades

Project Completed

Region 5: Eastern Oregon (Lostine, Wallowa, Wallowa)


​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Upgrade curb ramps in Wallowa and Lostine to meet Americans with Disabilities Act (ADA) standards.


Impacts

Traffic Impact

None.

Construction Impacts

​Access for pedestrians, including those with disabilities, will be available and identified through or around work zones. 

Meetings and Events

We held an online open house on June 4-18, 2021. The information presented in the open house remains available for review at the following link.​

Archive - Eastern Oregon ADA projects online open house.

Schedule

The project is complete.

Details

About

​This project will upgrade curb ramps in Wallowa and Lostine to meet Americans with Disabilities Act (ADA) standards.

Project elements include:
Enlarged project map.Wallowa:
  • ​Construct ADA curb ramps.
  • Install flashing beacons at South Clairmont Street between the Wallowa High School and parking lot entrance.
  • Bike lane striping on south side of OR 82 from Douglas Street to South Holmes Street.
  • Realign intersection of OR 82, South Holmes Street, Whiskey Creek Road and North Ellen Street.
  • Create cul-de-sac at North Ellen Street and OR 82.

Lostine:Enlarged project map.

  • Construct ADA curb ramps.

Location

OR 82 |
  • ​Wallowa: First Street through town - from North Madison Street, milepost 46.8, to South Wynema Street, milepost 47.6.
  • Lostine: from Roswell Street, milepost 54.7, to Elizabeth Street, milepost 55.0.

Cost and Funding

​The project is estimated to cost $24 million.

Contractor

​MJ ​Hughes Construction, Inc. | Vancouver, WA

Contacts & Media

Photo of OR 82 in front of Walllowa High School.

Project Contact

Region 5 Community Affairs Specialist
Vicki L Moles
Email
vicki.l.moles@odot.oregon.gov
Phone
541-620-4527

Last Updated

10/23/2023 1:47 PM

Project Number

22402