All applicable STIP projects that have an estimated total cost of $25 million or more are required to conduct a VE study regardless of the number of phases or unit breakdowns that have occurred on the project. For example, an urban interchange project, with an initial cost estimate of $40 million that has been separated into four $10 million projects due to funding shortages, would still be required to have a VE study. Estimated total project cost includes the estimate total of all financial cost to deliver the project as programmed in the STIP including planning, development, preliminary engineering, design, utility relocation, and construction, including but not limited to, the costs for environmental considerations, right of way acquisition, permitting, gee-environmental considerations, internal ODOT resources, consultant contracts and construction contracts.
VE Study Criteria
All STIP projects shall be evaluated for a VE study. Planning level studies can also benefit from VE studies. Projects that typically benefit from a VE study have one or more of the following attributes:
- Projects that exceed $25 million in estimated total project cost.
- Projects that have major structures.
- Projects that are complex.
- Projects that are designed by consultants.
- Projects that have largely exceeded preliminary cost estimates.
- Projects with alternative solutions to documented problems.
- Projects using critical or high cost materials and procedures.
- Projects with complex traffic staging.
- Projects that include extensive or expensive environmental or geotechnical requirements.
- Projects being considered for alternative contracting methods.
VE Study Exemption
Certain projects that do exceed $25 million in estimated total project cost, but do not include
one or more of the other attributes listed in the VE study criteria may not be good candidates
for a VE study. For these projects, the Transportation Project Manager (TPM) and/or Resident
Engineer-Consultant Projects (RE-CP) may submit a written request to the VE/Project Risk
Engineer to waive the VE study requirement for a project. No exemption will be granted for
projects that meet the following FHWA criteria requiring a VE study:
- Projects utilizing Federal-aid highway funding.
- Projects that are on the NHS.
- Projects exceeding $50 million in total project cost.
- Bridge projects exceeding $40 million in total project cost.
VE Study Timing
VE studies may be conducted during one or more project phases. In general, VE studies
performed during the project development phase have a greater potential for adding value
than VE studies performed during the project design phase. Some projects may not benefit
from a VE study, while others may benefit from several studies conducted at different times
and focusing on different aspects of the project.
Low Bid, Price Plus Time (A+B), or Price Plus Multi-Parameter (A+C+D) delivery
methods:
- Planning Phase - VE study to evaluate, refine, or reduce alternatives before going
ahead with project development. Types of projects include STIP, corridor,
reconnaissance, and Transportation System Plans (TSP). VE studies conducted in this
phase have the highest potential for enhancing project value.
- Development Phase - VE study prior to Design Acceptance Phase (DAP) completion. At this stage major project elements have been done. VE study to evaluate project
elements and limit alternatives for advancement. Design completion is about 10-15%.
- Design Phase - VE study to evaluate design details, materials, and staged construction.
- Construction Phase - VE study to evaluate and decrease major cost elements, potential
cost and schedule overruns, or to determine a triggered risk response action. A VE
study in this phase should be reserved for extreme cases only.
VE Study Facilitator
VE studies shall be led by a facilitator who is accredited as a Certified Value Specialist (CVS)
through SAVE International®.
VE Job Plan
VE is the systematic process of reviewing and analyzing the requirements, functions, and
elements of systems, projects, equipment, facilities, services, and supplies for the purpose of
achieving the essential functions at the lowest life-cycle cost consistent with the required
levels of performance, reliability, quality, and safety. The process is generally performed in a
workshop environment by a multidisciplinary team, which is facilitated by personnel that is
experienced, trained and certified in leading VE teams through the following phases of the
SAVE International® standard job plan:
- Information phase where the team gathers information to understand the project and
constraints.
- Functional analysis phase where the team identifies basic project functions and goals
and identifies any performance shortcomings or mismatches between identified
functions and customer needs for further study.
- Creative phase where the team conducts brainstorming to generate new ideas and
alternatives for improvements in a project, product, or process, with particular focus on
high cost variables, speed of execution, quality and performance.
- Evaluation phase where the team ranks ideas to find the best to meet the project value
objectives.
- Development phase where the team develops best ideas into viable alternatives for
improvement in a project, product, or process, with particular focus on high cost
variables, speed of execution, quality and performance.
- Presentation phase where the team presents recommended alternatives to the design
team.
- Implementation phase where the design team incorporates selected recommendations
into the project.
VE Study Implementation
Following the VE study, the TPM/RE-CP shall meet with the VE facilitator to discuss the
implementation disposition of recommendations identified in the VE study and to develop an
implementation plan for selected recommendations. Following the conclusion of this
meeting, the TPM/RE-CP shall prepare a report of implementation disposition that identifies
each VE recommendation as accepted, conditionally accepted, or rejected.
Rejection of VE Recommendations
The rejection of any individual VE recommendation or group of recommendations, on a single
project feature that may potentially save over $500,000, requires the signed approval of the
Region Manager and/or the Funding Program Manager.
VE Training
Recommended for anyone associated with transportation projects, but not required to be on
a VE study.