U.S. 26: Ten Eyck Road to Vista Loop Drive

Project Completed

Region 1: Portland metro and Hood River County (Sandy, Clackamas)


​We constructed over half a mile of new sidewalk on U.S. 26 in Sandy between SE Ten Eyck Road and SE Vista Loop Drive.​


Impacts

Construction Impacts

The majority of construction is complete. Expect periodic single lane closures. 

Meetings and Events

​While the majority of construction was complete in late 2022, summer weather brings ideal conditions to celebrate the new connection. ODOT and the City of Sandy will gather for remarks, refreshments and to enjoy the new sidewalk at 4:30 p.m. on Monday, July 17 at 39850 Pleasant Street in Sandy. All are welcome to join us! 

Schedule

Construction began in late February and was completed in late 2022. 

En Español:

La construcción comenzó a fines de febrero y se espera que continúe hasta fines de 2022.

Details

About

Project construction flyer/folleto de construcción del proyecto

The Oregon Department of Transportation installed more than half a mile of new sidewalk on the westbound (north) side of U.S. 26 between Ten Eyck Road/Wolf Drive and Vista Loop Road in Sandy in 2022. There was no sidewalk in this area, so people often used the shoulder of the highway. Now, the new six-foot-wide sidewalk to give people a safe place to walk and roll from the Sandy Vista Apartments into town to get to shops, the post office, Sandy Transit Center, and other destinations.​ 

Project area from Ten Eyck Road to Vista Loop in Sandy

A gravel shoulder separates the highway from a new sidewalk.

A new sidewalk runs along housing where there was previously a ditch.

A steep slope behind guardrail is transformed into a concrete sidewalk.

Location

U.S. 26 |

​U.S. 26/Mt. Hood Highway between SE Ten Eyck Rd. and SE Vista Loop Dr. in Sandy.

Cost and Funding

​The estimated construction cost for this project is $4.2 million.

En Español:​ 

El costo estimado de construcción para este proyecto es de $4.2 millones.

Benefits

​The new sidewalk provides a safe path for people walking and rolling on U.S. 26, where people previously had to walk along the highway shoulder.

Additional Information

​For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation/interpretation services, or more information call 503-731-4128, TTY 800-735-2900 or Oregon Relay Service 7-1-1.

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al (503) 731-4128. 

如果 您想了解这个项目翻译成简体中文的相关信息,请致电 (503) 731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.​

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону (503) 731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화​: (503) 731-4128. 


Contacts & Media

Project area between Ten Eyck Road/Wolf Drive and Vista Loop Drive in Sandy

Project Contact

Community Affairs Coordinator
Katelyn Jackson
Email
Katelyn.Jackson@odot.oregon.gov
Phone
503-731-8503

Get Project Alerts

Sign up for the newsletter!

Last Updated

9/19/2023 2:15 PM

Project Number

18823

Project Documents

Related documents to this project
K18823 US26 Ten Eyck to Vista Loop sidewalk construction flyer Feb 2022 Eng Esp bilingual.pdfU.S. 26 Ten Eyck Road/Wolf Drive to Vista Loop Road project construction flyer/folleto de construcción del proyecto