About
To help ease congestion and improve safety on Interstate 5 at Roberts Mountain, the Oregon Department of Transportation will construct a climbing lane on both approaches to the pass: southbound from milepost 117.7-116.3 and northbound from 115.3-116.8. ODOT will also repave the freeway in both directions between Roberts Creek (milepost 117.7) and the South Umpqua River (milepost 112.5). Substandard guardrail and median barrier will also be replaced.
Location
I-5
|
I-5 (MP 112.5-117.7): Project area is located about five miles south of Roseburg.
Cost and Funding
Funding: $30,428,900.00 (Statewide Transportation Improvement Program)
Total project cost: $32,826,871.20 (estimate)
Successful bid: $25,978,775.00 (Kerr Contractors; Nov. 1, 2018)
(Cost and funding figures updated Nov. 5, 2019.)
Contractor
Kerr Contractors (Woodburn, Oregon)