OR 126 Cornerstone Drive - Terry Street (Veneta to Eugene) Pavement Preservation Project

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Eugene, Veneta, Lane)


This project will replace the pavement between Veneta and Eugene and add safety improvements.​​

Impacts

Traffic Impact

Most w​ork will be done at night to minimize impact to travelers. Travelers should expect lane closures and reduced speeds in the work zone.

Construction Impacts

​Replacing a bridge rail just to the west of Fisher Road requires at least two weeks of continuous one-lane closures Sunday night through Friday morning. The highway will be fully open on weekends. That work begins in April.  

Schedule

​Beginning in mid-April:

  • New bus pullouts will be constructed near Ellmaker Road
  • Bridge rail will be replaced on a small bridge west of Fisher Road.

Trees were removed near Shady Rest Drive and Lake Side Drive over the winter to prepare for widening the north shoulder of the road.

Five and a half miles of new paving was completed in 2018, and 9000 feet of new guardrail installed. In 2019, another one and a half miles of paving will be done.

The project is scheduled to be complete in September 2019.

Details

About

​The pavement condition within this section of highway is deteriorated and needs repair. Areas have been patched and that repair work will continue until the full preservation project is underway. The project also includes safety improvements at various intersections on OR 126.

Location

OR 126 | ​Cornerstone Drive, Veneta to Terry Street, Eugene

Cost and Funding

​$8.5 million

Contractor

​Wildish

Benefits

This project includes many safety improvements identified by people in the community:

  • A right-turn lane at Ellmaker Road
  • Two bus pullouts
  • Centerline rumble strips. Shoulder rumble strips in locations where appropriate based on shoulder width and proximity to businesses. There will be no rumble strips in front of Veneta businesses.
  • Shoulder widening along the north side between Shady Rest and Lake Side Drive.
  • Grind/inlay and overlay paving of the entire section

Additional Information

I-105 Eugene-Springfield Highway has 24-hour lane closures as four bridges and ramps between the Delta Highway interchange and downtown Eugene are rehabilitated and brought up to current standards.

Contacts & Media

Project Map

Project 19743 Map Thumbnail

Videos


View on YouTube

Project Contacts

Project Manager
Steve Schultz
Email
steven.schultz@odot.state.or.us
Phone
541-757-4211

Public Information Officer
Angela Beers Seydel
Email
angela.beers-seydel@odot.state.or.us
Phone
541-726-2442