OR 58 Culvert Repair and Replacement Project

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Klamath, Lane)


​​​​​​​Repair or replace culverts along the highway that are in poor condition.


Banner image: Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time -try a new way or mode to get there or take a different route!

Impacts

Traffic Impact

Expect delays and lane closures. There will be multiple work zones with up to 20 minutes of delay.

Construction Impacts

We are working weekdays from 6 a.m. to 7 p.m. 

You can expect:

  • Shoulder closures.
  • Single lane closures weekdays between 6 a.m. -  7 p.m. with flagging.
  • Up to three work zones.
  • Potential delays up to 20 minutes.
  • Construction noise.​

Construction Activities

We are removing trees and clearing vegetation and utility work prepping for construction to start on April 3.

For the most up to date information visit TripCheck.com​.


Pedestrians, including those with disabilities, will have access through or around the work zone. ​

Details

About

​The OR 58 corridor is a lifeline route between the southern Willamette Valley (I-5) and Central Oregon (U.S. 97). There are several projects underway to explore how to help keep critical services accessible. This project identified 54 culverts needing repair or replacement because they are in poor or critical condition. The culverts are being reviewed to see if sizes need to be increased to address water flow or fish passage.

The shallow culverts will require digging trenches through the road and the deeper culverts will be replaced by drilling under the road.

This project is being developed by Western Federal Lands a division of the Federal Highway Administration.

​Schedule

Design: 2019-2022

Construction: 2023​​

Location

OR 58 |

​From I-5 to U.S. 97, milepoint 2.73 to 84.97, Lane and Klamath Counties​

Cost and Funding

​$12.6 million

Contacts & Media

Project Area Map

Project Contacts

Resident Engineer – Consultant Projects
Julie GaNung
Email
julie.e.ganung@odot.oregon.gov
Phone
541-726-2578

Public Information Officer
David House
Email
david.j.house@odot.oregon.gov
Phone
503-551-8641
Public Comment Form
Submit a commentfor project

Last Updated

4/24/2023 3:40 PM

Project Number

20102