About
Work at each site varies. Work includes, but is not limited to, replacing joints and bridge surfaces, and concrete repairs. All bridges will receive new railing and protective fencing.
New railings will replace rails that are not up to current safety standards.
Protective fencing will improve safety by preventing fallen and thrown objects from hitting people, vehicles or the highway.
Site 1: North 2nd Street over I-84 in La Grande
Work at this site is complete.
Site 2: OR 86 bridge over I-84 (Richland/Exit 302 Interchange) in Baker City
Work at this site is complete.
Site 3: McAlister Road over I-84 near La Grande
Work at this site is complete.
Site 4: Upper Perry Bridge (Bridge over I-84 at Exit 256 eastbound)
Work at this site is complete.
Site 5 and 6: Exit 259 I-84 off-ramp bridge
Work at this site is complete.
Location
I-84Cost and Funding
This project is estimated to cost $4.6 million.
Contractor
HP Civil, Inc. | Stayton, OR