OR 99 Junction City Paving Project

Project Completed

Region 2: Willamette Valley and Northwest Oregon (Eugene, Junction City, Lane)


​​​​​​​​​​​​​​​Paving preservation project.

Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Details

About

​OR 99 was repaved between 1st Avenue (milepost 109.63) and Enid Road (milepost 116.74), from Junction City to Eugene. The pavement was deteriorating so the surface layer was replaced to extend the road's useful life. The new surface provides travelers with a smoother ride and addresses safety concerns.

The work we completed included:

  • Paving highway between milepost 109.65 and 116.70.

  • Installing centerline rumble strips.

  • Upgrading curb ramps to meet Americans with Disabilities Act (ADA) requirements.

  • Upgrading pedestrian signals as necessary.

  • Replacing Junction City's weigh in motion system, used to capture truck traffic data without affecting traffic flow.

​Schedule

Construction 2022 - 2023

Location

OR 99 | ​Between Junction City and Eugene - 1st Avenue to Enid Road

Cost and Funding

​$7.3 million

Contacts & Media

Project Area Map

Videos


View on YouTube

Project Contacts

Resident Engineer
Shane Prohaska
Email
shane.prohaska@odot.oregon.gov
Phone
541-744-8080

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

2/5/2024 11:14 AM

Project Number

21235