U.S. 30: Millard and Bennett Roads (St. Helens)

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Columbia)


​​​​​​​​​​​​This project will improve the safety of U.S. 30 between Scappoose and St. Helens. ​​​​​​

construction banner

Impacts

Traffic Impact

Online Open House
Expect lane closures and delays. Alternate routes available.

Construction Impacts

Traffic on U.S. 30 will not be detoured, but side roads will have detours for access. See project area map​ for details.

Road Closure Information

Bennett Road:

  • West side stays closed for about two more months.

Millard Road:

  • East side closed from April 22 - July for rail work. ​

Work will be done Monday through Friday, from 6 a.m. to 5 p.m. There may be night work needed. 

Construction is estimated to be completed in 2022.

Meetings and Events

​Find out what road work is being done in 2022!

Visit our construction online open house to learn about the projects and the impacts to traffic that may occur as we work to build, repair and improve the roads that connect the communities of Region 2.

Sign up to receive future information about projects, road closures or invites to events. You can browse the different topics and sign up for the ones that interest you!


Details

About

​This project will improve the safety of U.S. 30 between Scappoose and St. Helens (from mileposts 25.7 to 27.2) in Columbia County by:

  • Increasing the turning radius of the right turn lane from U.S. 30 onto Bennett Road by widening and restriping the roadway near the intersection.
  • Restricting left turns onto U.S. 30 from Bennett Road by creating a median.
  • Adding a traffic signal at U.S. 30 and Millard Road.
  • Widening Millard Road to provide protected access to U.S. 30 from Millard Road.
  • Upgrading the rail crossings at both Millard and Bennett Roads, work to be completed by the railroad.

Schedule

Design though late 2020
Construction 2021 - 2022

Location

U.S. 30 | Between Scappoose and St. Helens 

Cost and Funding

​$7.5 million

Contacts & Media

Project Area Map

Project Contact

Resident Engineer
Jayson Buchholz
Email
jayson.w.buchholz@odot.oregon.gov
Phone
503-298-9180

Get Project Alerts

Sign up for the newsletter!

Last Updated

7/12/2022 5:53 PM

Project Number

21459