Project-Details







I-5 Paving: Santiam to Kuebler

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Salem, Marion)


​​​​​​​​​​​​​Replace the pavement and create a smoother ride.  


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

None at this time. When work starts again, you can expect lane closures, delays, detours for ramp closures and for speed to be reduced in the work zone.

Construction Impacts

None at this time. We plan to start work again in May. 

When we do, you can expect: 

  • Single lane closures: Sunday - Friday, 8 p.m. - 5 a.m.

  • Double lane closures: Sunday - Friday, 8 p.m. - 4 a.m.

  • On and off-ramp closures, one at a time: Sunday - Friday, 9 p.m. - 5 a.m.

  • Speed reduced to 50 mph in the work zone.​​

Construction Activities

None at this time. 

When we return, we'll install permanent reflective markers, rumble strips and do some pavement repairs. 

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. ​​

Details

About

The current pavement in the project area is in poor condition and rutting caused by the wear from vehicle wheel paths makes it vulnerable to winter weather.  ​Patching the road will continue to be a burden on maintenance until fixed. 

Last paved in 2008, this section of I-5 will have reached the end of its service life by the time construction starts in 2023.

This project includes:

  • Removing and installing new pavement from milepost 253.7 to milepost 251.1 on the northbound lanes and from milepost 253.7 to milepost 250.1 on the southbound lanes. 

  • Repave portions of the Kuebler Boulevard ramps. 

  • Install permanent striping and rumble strips.

  • Repair the rough road approaching the Turner Road and railroad overpasses on I-5. 

  • We will make some ADA improvements at the northbound I-5 on and off ramps on Kuebler Boulevard.​

Schedule

Design: 2020 - 2023
Construction: 2023​

Location

I-5 |

​Between Exit 253 and Exit 252

Cost and Funding

​$6.8 million

Contacts & Media

Project Map

Project Contacts

Assistant Resident Engineer
Doug Keys
Email
douglas.keys@odot.oregon.gov
Phone
503-510-9643

Public Information Officer
David House
Email
david.j.house@odot.oregon.gov
Phone
503-551-8641
Public Comment Form
Submit a commentfor project

Get Project Alerts

Sign up for the newsletter!

Last Updated

2/28/2024 4:07 PM

Project Number

21539