About
This is one of the main U.S. 101 intersections in town. The area is known to have high water and the traffic signal is outdated and needs to be replaced.
As part of this project, we will:
- Upgrade traffic signals. This will help improve traffic flow through the intersection.
- Install ADA curb ramps. These ramps improve mobility for everyone, whether you have a disability or not.
- Improve water drainage. This will help prevent water from pooling onto the road.
During construction you can expect noise, sidewalk, shoulder and lane closures.
We are planning to build and will have a better idea about the construction schedule and cost as we get further into design.
Schedule
Design: 2021-2026
Construction: 2027
Location
U.S. 101
|
Pacific Way
Milepost 18.8
Cost and Funding
Design and construction: $3,601,623
Pedestrians, including those with disabilities, will have access through or around the work zone.