U.S. 30: (10th Street) / Hughes Street Upgrades (Baker City)

Construction Phase

Region 5: Eastern Oregon (Baker City, Baker)


​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​We are modifying the intersection to improve ADA and freight mobility.


Slow down in work zone banner

Impacts

Traffic Impact

Expect Intermittent  shoulder closures throughout the project. ​

Meetings and Events

​We held an in-person open house February 23, 2023, at the Oregon Trail Electric Cooperative, Baker City Office, at 4005 23rd Street in Baker. ODOT staff was available to discuss project elements and answer questions.

We have compiled comments received during the open house into a Frequently Asked Questions document. It is posted at the bottom of this page.

Schedule

For the week of December 8:
Crews will be onsite for corrective work.
​​​This project is now expected to be completed in December.

Details

About

​​Improvements are needed on U.S. 30/10th Street on the northwest end of Baker City. Intersection enhancements will give trucks more room to turn safely on to U. S. 30 at Pocahontas Road.

Pedestrian improvements will be added along the west side of U.S. 30 to fill in gaps of missing sidewalks or replace those in poor condition, and new curb ramps will be constructed to meet current ADA standards.

Work on Cedar Street will be led by Baker City.​

Location

U.S. 30 |
10th Street:
  • Intersection with Hughes Lane/Pocahontas Road.
  • ​Curb ramp and sidewalk improvements from L Street to Boulevard Street. The majority of work will be on the west side, with some improvements on the east side of 10th Street.

Cost and Funding

​The project is estimated to cost $12.1 million.

Contractor

​​Moreno & Nelson Construction.

Contacts & Media

Aerial photo of U.S. 30 at Hughes Lane and Pocahontas Road.

Project Contact

Community Affairs Specialist
Vicki L Moles
Email
vicki.l.moles@odot.oregon.gov
Phone
541-620-4527

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/5/2025 10:15 AM

Project Number

21643