U.S. 30: (10th Street) / Hughes-Cedar Street Upgrades (Baker City)

Design Phase

Region 5: Eastern Oregon (Baker City, Baker)


​​​​​​​​​​Modify the intersection to improve ADA and freight mobility.


Impacts

Meetings and Events

​We held an in-person open house February 23, 2023, at the Oregon Trail Electric Cooperative, Baker City Office, at 4005 23rd Street in Baker. ODOT staff was available to discuss project elements and answer questions.

We have compiled comments received during the open house into a Frequently Asked Questions document. It is posted at the bottom of this page.
Comments can still be made via either project contact listed to the right of this webpage.

Schedule

​Design 2022-2023.

Goes to bid early 2024.

Construction 2024-2026.

Details

About

Enlarged project map.​Improvements are needed on U.S. 30/10th Street on the northwest end of Baker City. Intersection enhancements will give trucks more room to turn safely on to U. S. 30 at Pocahontas Road.

Pedestrian improvements will be added along the west side of U.S. 30 to fill in gaps of missing sidewalks or replace those in poor condition, and new curb ramps will be constructed to meet current ADA standards.

Work on Cedar Street will be led by Baker City.

*Project is in design. Project limits and scope are not finalized.

Location

U.S. 30 |
10th Street:
  • ​At intersection with Hughes Lane/Pocahontas Road.
  • ​From Hughes Lane/Pocahontas Road to E Street, west side.

Cost and Funding

​The project is estimated to cost $8.8 million.

Contacts & Media

Aerial photo of U.S. 30 at Hughes Lane and Pocahontas Road.

Project Contacts

Region 5 Community Affairs Specialist
Vicki L Moles
Email
vicki.l.moles@odot.oregon.gov
Phone
541-620-4527

Region 5 Transportation Project Manager
Grant Matlock
Email
grant.matlock@odot.oregon.gov
Phone
541-963-1374

Get Project Alerts

Sign up for the newsletter!

Last Updated

9/19/2023 2:17 PM

Project Number

21643