OR 6: Devils Lake Fork Wilson River Bridge

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Tillamook)


​​​​​​​​​​We're making structural upgrades and repairs to preserve the bridge.​


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​Expect crews working during the day and single lane closures with an automated flagging assistant device to control traffic through the work zone. Drive with caution and watch for workers. 

Construction Impacts

automated flagger assistant device gifYou can expect:

  • Crews working during the day.
  • Single lane closures with an automated flagging assistant device to control traffic through the work zone between:
    • 7 a.m. to 5 p.m. Monday through Thursday.
    • 7 a.m. to 12 p.m. on Fridays.
  • Most of the work to be under the bridge.
  • Construction noise and delays.
  • The bridge to be weight-restricted for the duration of the project. 
Icon of the front of a semitruckIf you drive a semitruck or similar heavy vehicle, expect this bridge to be weight restricted during construction to permit weight tables 3 through 5. Please review the Commerce and Compliance Division's CCD's webpage on weight tables webpage to learn more.

Construction Activities

We're making repairs to strengthen and preserve the bridge. ​

​Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. ​​​

Details

About

enlarged project map iconWe're working on the Devils Lake Fork Bridge that crosses the Wilson River on OR 6. This bridge is on an important tourist and freight route between the Portland area and the coast.

We are: 

  • ​Removing the rust.
  • Replacing worn out or damaged bolts and rivets as needed. 
  • Applying a new layer of paint to help preserve the bridge.

Schedule

Design: 2021-2024

Construction: 2025-2026

Location

OR 6 |

​Milepost 32

Cost and Funding

​Design and construction: ​$6,514,875​

Contacts & Media

project area map

Project Contacts

Resident Engineer – Consultant Projects
Anita Eaton
Email
anita.c.eaton@odot.oregon.gov
Phone
971-403-8522

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045