Skip to main content

Oregon State Flag An official website of the State of Oregon »

Project-Details







OR 6: Devils Lake Fork Wilson River Bridge

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Tillamook)


​​​​​​​We're making structural upgrades and repairs to preserve the bridge.​


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​None at​ this time. We anticipate starting construction in February 2026.

Construction Impacts

automated flagger assistant device gifWe plan to start work in February 2026. When construction starts, you can expect:

  • Most of the work will be under the bridge.
  • Lane closures with an automated flagging device to control traffic through the work zone.​
  • Construction noise and delays.

Construction Activities

None at this time.

​Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. ​​​

Details

About

enlarged project map iconWe're working on the Devils Lake Fork Bridge that crosses the Wilson River on OR 6. This bridge is on an important tourist and freight route between the Portland area and the coast.

We are: 

  • ​Removing the rust.
  • Replacing worn out or damaged bolts and rivets as needed. 
  • Applying a new layer of paint to help preserve the bridge.

Schedule

Design: 2021-2024

Construction: 2025-2026

Location

OR 6 |

​Milepost 32

Cost and Funding

​Design and construction: ​$6,514,875​

Contacts & Media

project area map

Project Contacts

Resident Engineer – Consultant Projects
Anita Eaton
Email
anita.c.eaton@odot.oregon.gov
Phone
971-403-8522

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/2/2025 2:53 PM

Project Number

21737