Skip to main content

Project-Details





OR 99W Curb Ramp Project - SE Chapman Place to SW McKenzie Ave

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Corvallis, Benton)


​​​​​​​​​​​​​​​Rebuilding curb ramps to current ADA guidelines.


Construction Banner

Impacts

Traffic Impact

​Construction has started, there will be intermittent outside lane closures of OR 99W/SE Third Street that may result in minimal delays. Work will occur between 9 a.m. and 4 p.m. Monday - Friday. 

Construction Impacts

​​Interactive Map IconConstruction crews began on February 8 to work on ADA curb ramps in south Corvallis. The project will be split into 2 phases. The first phase has started and will focus on constructing new ADA ramps at 17 different existing street corners and the second phase will complete the remaining 35 locations starting in July 2021.​

What to expect during construction:​
  • There will be noise and dust during work hours. 
  • Pedestrians, including those with disabilities, will have access through or around work zones.
  • Notice of upcoming pedestrian detours will be placed along sidewalks at least one week in advance.
  • When pedestrian detours are used across unmarked crosswalks, additional temporary crosswalk signing will be used wherever possible.
  • Watch out for signs about bicycles sharing the roadway through work zones.
  • Law enforcement will be patrolling the corridor during construction.
  • Only one corner of each intersection will be closed at a time. 
  • Work may occur at multiple intersections at the same time. 
  • Some work may require lane closures.
  • Work is expected to be done during the daytime from local streets and along OR 99W outside of peak traffic periods. 
  • Nighttime lane closures may be needed, especially north of Alexander Avenue, during certain times of the year.

​Pedestrians, including those with disabilities, will have access through or around work-zones.

Details

About

Inspector on SidewalkWe are committed to providing the best accessibility possible to all people using the transportation system.  One of the ways we are doing this is by bringing curb ramps along our highways up to current ADA accessibility guidelines. We’re also exploring ways to design and construct these ramps more efficiently. 

This project will rebuild 52 street corners in Corvallis from SE Chapman Place to SW McKenzie Avenue. ​


​​Schedule

Design: 2020

Construction: 2021​

Location

OR 99W |

​​Corvallis

Cost and Funding

​​$2 million

Contacts & Media

Project Area Map

Videos


View on YouTube

Project Contacts

Transportation Project Manager
Julie GaNung
Email
julie.e.ganung@odot.state.or.us
Phone
541-726-2578

Public Information Officer
Angela Beers Seydel
Email
angela.beers-seydel@odot.state.or.us
Phone
541-726-2442

Get Project Alerts

Sign up for the newsletter!

Last Updated

2/11/2021 5:59 PM

Project Number

22117



Your browser is out-of-date! It has known security flaws and may not display all features of this and other websites. Learn how

×