Traffic Impact
Expect daytime lane closures with flaggers or signal control and delays up to 20 minutes.
Construction Activities
During construction for guardrail installation and work on West Fork Dry Creek Bridge and Eagle Creek Bridge, traffic will be controlled by:
- Daily, single-lane closures controlled by automated flagging devices.
At North Pine Creek Bridge, traffic will be controlled by:
- A temporary traffic signal operating 24/7.
All travelers can expect delays up to 20 minutes.
Schedule
For the week of June 1:
Guardrail replacement:
Crews continue replacing guardrail. Expect work between Copperfield and 2 miles west of town, mileposts 69.5-71.
Bridge work will continue at North Pine Creek Bridge, 9 miles east of Halfway (milepost 63.5), with temporary traffic signals.
All work is scheduled to be completed by the end of June.