Much of the guardrail in Oregon is outdated. There are several locations along our highways where the guardrail at the bridge ends is either missing or is not connected.
For this project, we are:
- Upgrading the outdated guardrail along OR 6.
- Installing new guardrail at bridge ends where it is missing.
- Replacing curb ramps at the bridge between Mills Bridge Road and Pete Street to make them ADA compliant.
Guardrail helps lessen the severity of a crash and make the roads safer for drivers.
Schedule
Design: 2023-2025
Construction: 2026-2027
Location
OR 6
|
Milepost 0 - 51.5
Cost and Funding
Design and construction: $10,385,753