Skip to main content

Project-Details





Paving Preservation Project - Salt Creek Tunnel to Milepost 70

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Lane)


​​​​​Road, culvert and bridge work being done in the corridor.​


Construction Banner

Impacts

Traffic Impact

Online Open House

Expect construction noise, lane closures and delays. Work zone will be controlled by flaggers using pilot cars.

Construction Impacts

​Expect nighttime work Sunday night through Friday morning, 7 p.m. to 7 a.m.

We will start work on the east end of the project and work towards the tunnel, completing both lanes as we move along the corridor.​

Meetings and Events

​Find out what road work is being done in 2022!

Visit our construction online open house to learn about the projects and the impacts to traffic that may occur as we work to build, repair and improve the roads that connect the communities of Region 2.

Sign up to receive future information about projects, road closures or invites to events. You can browse the different topics and sign up for the ones that interest you!

Details

About

view enlarged project mapPaving Preservation Project - Salt Creek Tunnel to Milepost 70

The pavement is in poor condition and we are replacing it to preserve the road structure and provide travelers with a smooth ride. 

Location

OR 58 |

​From I-5 to OR 97

Cost and Funding

Total budget $15.6 million

Contacts & Media

Project Area Map

Project Contacts

Assistant Resident Engineer
Doug Kirk, PE
Email
douglas.w.kirk@odot.oregon.gov
Phone
541-736-9164

Public Information Officer
Angela Beers Seydel
Email
angela.beers-seydel@odot.oregon.gov
Phone
541-726-2442

Get Project Alerts

Sign up for the newsletter!

Last Updated

7/15/2022 1:52 PM

Project Number

22514