This project continues with planned improvements to the Beltline/Delta Interchange to make the area safer and relieve congestion.
For this project, we're planning to:
-
Widen and raise the existing bridge over Beltline Highway.
-
Add one lane to southbound Delta Highway from Green Acres Road to the Goodpasture Road interchange.
-
Add a second left-turn to the westbound Beltline Highway off-ramp onto Delta Highway.
-
Upgrade the traffic signal at the Beltline Highway and Delta Highway interchange.
Schedule
Design: 2024-2026
Construction: 2027-2028
Location
OR 132
|
Delta Highway | From milepost 0 to .6
Cost and Funding
Design and construction: $22,574,667