OR 6 at Wilson River Loop East Safety Improvements

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Tillamook, Tillamook)


​​​​​We're making improvements to make this intersection safer.​


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​None at this time.

Construction Impacts

​When construction starts, you can expect: 

  • Lane and shoulder closures as needed.
  • Construction noise and delays.

Construction Activities

We plan to start construction in late 2026 or in 2027.​

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not.

Details

About

enlarged project map iconThe intersection between OR 6 and Wilson River Loop East has poor visibility when turning right or left. This has caused fatal and serious injury crashes. 

We're planning to:

  • Widen and build a buffered right-turn lane.
  • Install new signs. 

Our goal is that these improvements will help make the intersection safer, reducing fatal and serious injury crashes. 

We're planning to build and will have a better idea about the schedule and construction cost as we get further into design. 

Schedule

Design: 2023-2026

Construction: 2026-2027​

Location

OR 6 |

​Milepost 2.07, Wilson River Loop East

Cost and Funding

​Design and construction: $3,900,039

Contacts & Media

project area map

Project Contacts

Transportation Project Manager
Ian Roholt
Email
ian.roholt@odot.oregon.gov
Phone
541-745-9168

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/31/2025 12:42 PM

Project Number

22706