About
We're improving a two mile rough section of pavement on OR 18 by the OR 99W interchange. The repairs are needed to preserve the road, reduce maintenance costs and give you a smoother ride.
We are:
- Keeping the existing road alignment.
- Reviewing existing drains to make sure they are operating correctly.
- Removing and replacing the driving surface.
- Maintaining height for vehicles under existing overhead sign and signal crossings.
- Replacing curb ramps as needed to meet American with Disabilities Act (ADA) standards.
- Installing new permanent striping.
We are planning to build and will have a better idea about the construction schedule and cost as we get further in design.
Schedule
Design: 2024 - 2026
Construction: 2027
Location
OR 18
|
S McMinnville Interchange - E McMinnville Interchange
Cost and Funding
Design and construction: $11,822,677
Pedestrians, including those with disabilities, will have access through or around the work zone.
Project information may differ from what is published on the Transportation Project Tracker, which pulls from a system updated quarterly as changes are approved.