Banks Highway Lighting Replacement

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Banks, Washington)


​​​​​​​​​​​We're replacing light poles at two OR 6 interchanges in Banks.​


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​None at this time. We plan to start construction in summer 2026.

Construction Impacts

​When construction starts, you can expect:

  • ​Shoulder and lane closures.
  • Construction noise and delays.

Construction Activities

​None at this time.

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not.

Details

About

enlarged project map iconWe're looking at light poles on OR 6 at the OR 47 and U.S. 26 interchanges​ to replace in the future since they are in poor condition.

Find out where the light poles are located by looking at our interactive project map.

The new light poles will have LED light bulbs. Some of the benefits of LED lighting over the current bulbs are that they:

  • interactive project mapLast longer an​d are more energy efficient.
  • Are more environmentally friendly.
  • Don't produce heat and are more reliable.
  • Are brighter with a more consistent and wide light pattern, meaning less dark spots.

Schedule

Design: 2024 - 2026

Construction: 2026 - 2027

Location

Multiple |

OR 6 and OR 47 Interchange
OR 6 and U.S. 26 Interchange

Cost and Funding

Design and construction: ​$1,738,310​

Contacts & Media

project area map highlighting work on the OR 47 and OR 6 interchange

Project Contacts

Transportation Project Manager
Charles Stouder
Email
charles.stouder@odot.oregon.gov
Phone
503-302-3874

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/8/2025 3:38 PM

Project Number

22797