About
The New Youngs Bay Bridge is one of the connecting roads between Warrenton and Astoria. It needs repair between mile points 4.5 to 5.4.
As part of this project, we're replacing the bridge driving surface and guardrails.
This will help increase the bridge life and improve driver safety.
We're planning to build and will have a better idea about how much construction will cost further into design.
Schedule
Design: 2024-2028
Construction: 2029
Location
U.S. 101
|
Between Astoria and Warrenton
Cost and Funding
Design and construction: $12,900,872
Pedestrians, including those with disabilities, will have access through or around the work zone.
Project information may differ from what is published on the Transportation Project Tracker, which pulls from a system updated quarterly as changes are approved.