Traffic Impact
In Hermiston:
Sidewalk, lane and/or shoulder closures.
Watch for flaggers, cones and signs.
Access to businesses will remain open during construction.
All pedestrians will have access through or around work zones.
Schedule
For the week of April 20:
Crews are working at these locations:
- U.S. 395 in Hermiston:
- Work at Theater, Gladys, Elm and Highland.
- Concrete pours planned for Dogwood, Catherine and June avenues.
- OR 207:
- Work at Ridgeway and pedestrian crossing at Joseph.
- Work on pedestrian poles is also in progress.
This project is scheduled for completion by July 2026.
Schedules are subject to change.
There is a temporary stop sign that needs to be replaced in Irrigon. Otherwise, work in Irrigon and Charleston is finished.
We just finished work in Hermiston. Why are we returning?Due to the number of curb ramps in Hermiston, we split work into two phases. Phase 2A was completed mid-October 2025.