This is an important route whether you walk, drive, ride or roll. This project is the second phase of a larger pedestrian improvement effort led by the City of Warrenton. The goal is to provide safe access from Warrenton Grade School to Warrenton High School.
With this project, we're looking to:
- Construct a sidewalk on a single side of Main Avenue/OR 104.
- Complete ADA curb ramp improvements.
- Upgrade signs, striping and lighting.
- Install enhanced pedestrian crosswalks at key locations.
We're looking at what improvements can be made in the project area and what it will cost. We'll have a better idea about the schedule, cost and what we can build as we get further into design.
Schedule
Design: 2025
Construction: Not currently scheduled. Estimated to start in 2026.
Location
OR 104
|
Main Avenue | Milepost 3.99 - 4.65
Cost and Funding
Design and construction: $4,015,658
Pedestrians, including those with disabilities, will have access through or around the work zone.