Traffic Impact
North Powder:
Sidewalk, lane and/or shoulder closures.
Watch for flaggers, cones and signs.
Access to businesses will remain open during construction.
All pedestrians will have access through or around work zones.
Meetings and Events
We met with city councils in November 2024 to provide project updates. The public was invited to attend.
- North Powder: Monday, Nov. 4, 7-9 p.m.
- Halfway: Thursday, Nov. 14, 5-7 p.m.
- Richland: Friday, Nov. 15, 3:30-5:30 p.m.
Schedule
For the week of March 23:
North Powder: Crews will be setting up traffic control and temporary signs, and saw cutting existing corners to begin replacing ramps. Work in North Powder is exptected to go into early June.
Summer 2026:
- Halfway: work is tentatively scheduled for June and July.
- Richland: work is tentatively scheduled for late July into September.
The project is scheduled to be completed October 2026.