Schedule
Project design 2024-2026. Designed under project K22754.
Sidewalk drilling took place Monday, Dec. 29, 2025.
Hazmat soil sampling was completed the week of March 2, 2026.
Project bid date has changed from March 2026 to June 2026.
Expected construction 2026-2027.