Skip to main content

Oregon State Flag An official website of the State of Oregon »

Project-Details







OR 99W: Amity ADA Curb Ramps

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Amity, Yamhill County)


​​​​​​​​​​​​​​We're upgrading and installing new curb ramps to improve accessibility for all.​​​


Design Banner showing a community of pedestrian and bicyclists with text: Improving Access Whether You: Drive, Ride, Walk or Roll.

Impacts

Traffic Impact

Please use caution, slow down and watch for workers.

Construction Impacts

When construction starts, you can expect:

  • Crews working during the day, Monday through Thursday and Friday as needed. 
  • Lane shifts, shoulder and lane closures with flaggers helping direct traffic as needed. 
  • Delays and construction noise – saw cutting can be loud. 
  • Businesses near the corners we're working on to remain open during construction.

Construction Activities

You may see crews in the area doing survey work to prepare for construction to start in early 2026.

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. ​

Details

About

​We are bringing curb ramps along our highways to current American with Disabilities Act (ADA) accessibility standards. ​As part of the project we'll look at existing crosswalks to see if they should remain or be removed. We may also add curb ramps where they don’t currently exist or pedestrian push buttons at some crosswalks.​

This project will rebuild approximately 75 existing curb ramps in Amity.   

This might include:

  • Minor work, such as fixing a ramp that is too steep or moving pedestrian push buttons at crosswalks.
  • Installing crosswalk closed signs if the crossing is considered unsafe.
  • Rebuilding or building a new ramp if needed.

Most corners in the project area only need minor work or signs but some corners will require a full rebuild or installation.

Why are ADA curb ramps important?

ADA curb ramps provide access between the sidewalk and road for people using wheelchairs, strollers, walkers, hand carts, bicycles and also for pedestrians who have trouble stepping up and down high curbs. We're adding textured plates at the curb ramps, called truncated domes. These allow pedestrians to feel, see and hear where the crossing is located and the direction they should go to safely cross the street.

ADA curb ramps benefit everyone regardless of whether they have a disability. By making curb ramps gently slope to the road, it improves accessibility and promotes safer travel between the sidewalk and road.

Why aren’t all the curb ramps in my community being fixed at the same time?

Once we review each corner, we will group and rebuild curb ramps in stages at various locations in the Willamette Valley and Northwest Coast.

Not all intersections or curb locations are the same, some are construction-ready and others may have fire hydrants, utility boxes, utility poles, additional land requirements or we need an environmental permit. These are things we consider when scheduling the curb ramp construction in each city.

The construction-ready locations are done first because they can be done immediately while those needing additional coordination or design will be part of a future stage of construction. This is why an intersection with four corners might be completed at different times.

​By making these accessibility improvements, whether you drive, ride, walk or roll, we are committed to providing the best accessibility possible to all people using the transportation system. 

Click here to sign up for email updates. Sign up for email alerts to get updates on the project!

Schedule

Design: 2023 - 2024
Construction: 2025 - 2026

Location

Multiple |

​​OR 99W | Milepost 44.2 to 44.8
OR 153 | Milepost 6.1 to 6.6, Stanley Street to Goucher Street

Cost and Funding

​Design and construction: $3,336,000​​

Contacts & Media

project area map

Project Contacts

Project Leader
Wade Luckman
Email
wade.luckman@odot.oregon.gov
Phone
541-419-2085

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/8/2025 4:07 PM

Project Number

N00030