Project
The park reopened on July 1, 2024, after an 11-month closure for construction.
The project focused on upgrading the park and campground utilities, including power and water lines. The upgrades included:
- Replacing single-phase power to three-phase power so onsite equipment can operate safely.
-
The local power provider will also replace the overhead power lines with underground power lines in conduit.
- Replacing portions of the water lines that are well beyond replacement age and are an ongoing maintenance issue.
- Rehabilitating a sewer lift station with new pumps and controls.
- Paving and campsite improvements.
Milestones
Project Investment
We estimated the general obligation bond to be $5-6 million. At the completion of the project, we had spent $6.8M.
Last updated Oct. 2025.