North Canyon trailhead parking area and day-use restroom when it was under construction.
North Gateway Visitor Center under construction.

About Silver Falls State Park
Silver Falls State Park is renowned for its waterfalls and a 35-mile trail network for hikers, mountain bikers and equestrians. The Trail of Ten Falls, a spectacular, nationally recognized hiking trail weaves through a temperate rainforest in the western Cascade Mountain foothills.The trail passes a series of breathtaking waterfalls along a rocky canyon, and descends to winding Silver Creek at the forest floor.
Project
A portion of this GO Bond project has been put on hold until additional funding becomes available. Oregon State Parks is focusing on projects that will extend the life of existing facilities rather than adding new ones due to budget constraints. OPRD will allocate any remaining GO Bonds to its maintenance backlog.
Developing the North Gateway will bring more campsites to the park and increase campsite inventory to the statewide park system. Improvements include:
- North Gateway campground and restroom/shower facilities. (On hold)
-
Infrastructure improvements such as water, electrical, and sewer systems, as well as relocation of the current RV dump station. (Portions on hold)
- North Gateway Visitor Center. (In progress)
- New North Canyon trailhead and parking lot, which will help parking congestion in the South Falls and Winter Falls parking areas. (Complete)
Visitor impacts
There will be minimal impact on visitors during construction.
Milestones
- North Gateway tree thinning completed.
- North Canyon trailhead and day-use area opened July 2023 with a new trailhead and parking lot to help with congestion in the South Falls and Winter Falls parking areas. Includes 59 new parking spots and renovated ADA bathroom
- Wetland delineation report completed.
- RV dump station construction completed.
Next Steps
- Planning and design for Visitor Center construction.
- Begin the final phase of construction on the North Gateway Visitor's Center.
The following steps are on hold and may be resumed at a later date:
- Planning and design for campground construction.
- Begin campground construction.
The current general obligation bond estimate is $10-12 million.
Last updated Nov. 2025. Additional updates as information becomes available.