Facilities

The Carty Generating Station is a 450 MW combined-cycle natural gas-fueled electric generating power plant. The facility was previously approved to consist of up to two 450-megawatt, combined-cycle electric generating turbines (Unit 1 and Unit 2). Unit 1 was constructed and placed in service in July 2016. The construction deadline for Unit 2 has passed and therefore, Unit 2 and all related or supporting facilities that were previously approved but not built are no longer authorized, including the 18-mile 500 kV transmission line to the Slatt Substation in Gilliam County. PGE has requested EFSC approval of site certificate amendment 1 to construct and operate an approximately 50 MW solar PV facility.

Under Review/Operating. In August 2016, PGE submitted a request to amend the site certificate to extend the construction deadline for the previously-approved Unit 2 natural gas power generating facility, add a Unit 3 natural gas power facility, and add an approximately 50 MW solar PV facility. In May 2017, prior to an EFSC decision on that amendment request, PGE suspended the review. On February 20, 2018, ODOE received a revised amendment request from PGE. The revised amendment request includes only the 50 MW solar PV facility on approximately 300 acres.

As the original amendment request was received by ODOE in 2016, the request is being processed under the EFSC rules and administrative procedures that existed at that time. The Department has issued public notice and is currently accepting public comments on the amendment request. Comments must be submitted in writing to the Department and must be received by April 6, 2018 at 5 p.m. Please see the public notice for additional information regarding submittal of comments.​
Morrow County. Ma​p​​
Applicant/Certificate holder: Portland General Electric
ODOE contact: Max Woods
Applicant/Certificate holder contact: Arya Behbehani
​​​​​​​​​​​​​

Project Amendment(s)

​​
  
Description
  
02/22/2018
03/05/2018
​​​ 

Project Timeline

  
Description
  
Preliminary Application Received
01/05/2010
Complete Application
05/10/2011
06/29/2012
07/02/2012
​​
​​​​​​​​​​​​​​​​
​Contact the Facility Siting Team:
​​​​​​​​​​​​​​​
​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​ ​​

Exhibit Files Reference

  • Exhibit A: Applicant Information 
  • Exhibit B: Project Description
  • Exhibit C: Property Location and Maps
  • Exhibit D: Organizational Information
  • Exhibit E​: Permits Required
  • Exhibit F: Property Ownership 
  • Exhibit G: Materials Analysis
  • Exhibit H: Geology and Soil Stability 
  • Exhibit I: Soils
  • Exhibit J: Wetlands
  • Exhibit K: Land Use
  • Exhibit L: Protected Areas
  • Exhibit M: Financial Analysis
  • Exhibit N​: Non-generating Facility Information
  • Exhibit O: Water Requirements
  • Exhibit P: Fish Wildlife Habitat 
  • Exhibit Q: Threatened and Endangered Plants and Animals
  • Exhibit R: Scenic Aesthetic Values 
  • Exhibit S: Cultural Resources
  • Exhibit T: Recreational Facilities 
  • Exhibit U: Public Services
  • Exhibit V​: Waste Minimization 
  • Exhibit W: Site Restoration
  • Exhibit X: Noise 
  • Exhibit Y: Carbon Dioxide Emissions 
  • Exhibit Z: Cooling Towers  
  • Exhibit AA: EMFs – Electric and Magnetic Fields
  • Exhibit BB: Other Information
  • Exhibit CC: Additional Statutes Rules Ordinances
  • Exhibit DD​: Other Specific Standards