U.S. 101: Devils Lake Outlet, Schooner Creek and Siltcoos River Bridges Cathodic Protection Project

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Dunes City, Lincoln City, Lane, Lincoln)


​Three bridges on U.S. 101 Oregon Coast Highway will be repaired and cathodic protection installed. Devils Lake Outlet and Schooner Creek Bridges are in Lincoln City. Siltcoos River Bridge is near Dune City, just south of Florence. ​​​

Impacts

Traffic Impact

D River:
Work has been underway since the first week of February 2019. Work will continue during the day until Labor Day weekend when work will become a mix of day and night work. During night work, expect intermittent lane closures with flaggers. 

Pedestrian access will be available on one side of the bridge at all times.

Schooner Creek: 
Night work begins on Schooner Creek Bridge on Tuesday, September 10. Lanes will be closed and traffic flagged through the work zone. Travelers should expect minor delays between 8 p.m. and 6 a.m. at the southern entrance to Lincoln City.


​Expect intermittent lane closures. Single lane closures will be allowed at night when traffic volumes are lower. Temporary traffic control will be in place to guide travelers through the work zone. Sidewalks on each side of the bridges will be closed periodically. Occassionally, it may look like there is nothing happening in a closed lane, but our crews are likely repairing cracks under the bridge. Traffic can't use the location above the repair sites while cracks are being repaired from underneath. 

Temporary, accessible pedestrian routes will be provided to direct pedestrians around the work zones. Access to nearby businesses will be maintained at all times. Check TripCheck.com for construction status and current travel conditions.

Construction Impacts

Hydroblasting the bridges to remove the bridge rails for replacement and spraying zinc coating for the cathodic protection are noisy. Neighbors will be notified of construction schedules and what to expect. 

Meetings and Events

An open house was held August 22, 2018, in Lincoln City. 

Key Milestones

​Work began on the D River Bridge in September 2018. Schooner Creek Bridge is scheduled to begin in early summer 2019, and Siltcoos River Bridge begins in spring 2020.

Schedule

​Construction is scheduled for 2018 - 2021.

D River:

  • Construction began in September 2018, scheduled to last 16 months
  • Construction hours will vary based on the activity Winter -Spring - Fall
  • Summer construction hours: 6 a.m. to 10 p.m.
  • June 1 - September 1: no work allowed 10 p.m. to 6 a.m.
    • Exception - a few nights of paving, announced in advance

Schooner Creek:

  • Began July 15, 2019, and is scheduled to last 21 months
  • Night time closures begin September 10.
  • Lanes will be closed from 8 p.m. to 6 a.m.
  • Traffic is flagged through the work zone during lane closures
  • Year-around construction of 10 hour shifts

Siltcoos River:

  • Will begin in April 2020, scheduled to last 18 months
  • Construction hours are TBD 

Details

About

  U.S. 101Bridges - 3 bridges.jpg

​Three bridges will be repaired and updated, including removing and repairing corroded bridge structural pieces and railings. Cathodic protection will also be installed. 

D River 2.jpg
D River Bridge, Lincoln City

Schooner Creek 2.jpg

 




Schooner Creek Bridge, Lincoln City

 

 



 

Siltcoos.jpg 

Siltcoos River Bridge, Dune City

Location

U.S. 101 | ​Lincoln City and Dune City, south of Florence

Cost and Funding

$11.782 million for planning and construction

Contractor

​Freyssinet Inc.

Benefits

​These bridges have deteriorated from the salt air on the coast and are in need of repair. If nothing is done, the bridges would eventually have to be replaced. They might also need to be load rated, meaning that large vehicles over a certain weight would not be able to travel over them.

What Problem Will This Improve?

​This is one of a series of bridge cathodic protection projects along the Oregon Coast, designed to keep the structures in service for years to come.

Additional Information

​The bridges will receive titanium and steel reinforcements on the bridge deck and along the girders under the bridge to strengthen them. This will require cutting narrow slots and drilling small holes to insert the reinforcements, which will then be secured to the bridge with an epoxy.
 
Bridge rails will be replaced with new rails that meet current standards. A variety of methods will be needed to remove the old rail while not damaging portions of the bridge that remain, including chipping and hydro-demolition.
 
The bridges will also receive cathodic protection, which provides a shield of protective coating to prevent the steel from corroding.

Contacts & Media

Project Map

Project 18599 Map Thumbnail

Project Contacts

Resident Engineer
Steve Schultz
Email
steven.schultz@odot.state.or.us
Phone
541-757-4211

Public Information Officer
Angela Beers Seydel
Email
angela.beers-seydel@odot.state.or.us
Phone
541-726-2442

Get Project Alerts

Sign up for the newsletter!

Last Updated

10/7/2019 11:52 AM

Project Number

18599