Project-Details







Viento State Park to Mitchell Point (Phase 2)

Construction Phase

Region 1: Portland metro and Hood River County (Hood River, Hood River)


​​​​​​​​We are paving the remaining 0.7 mile gap of the Historic Columbia River Highway State Trail between Viento State Park and the Mitchell Point Tunnel to reconnect nearly 10 miles of ADA-accessible car-free trail.​


https://www-auth.oregon.gov/odot/Projects/Project%20Images/I-84-HCRH-banner.png

Impacts

Traffic Impact

During construction expect periodic shoulder closures and minimal I-84 eastbound right lane closures during concrete pours for the Perham Creek bridge.

The Historic Highway State Trail is temporarily closed to all users two miles east of Viento State Park, including hikers and bikers, while we pave the 0.7 mile gap between Perham Creek and Mitchell Point. 
Learn more.

Viento State Park and the Mitchell Point Tunnel will remain open throughout construction.  

Visitors can access the tunnel by parking in the Mitchell Point Tunnel parking lot (Exit 58). 

​Expect periodic shoulder closures on I-84 within the project area.

Construction Impacts

Construction activities are underway. 

During construction, expect periodic shoulder closures and minimal I-84 eastbound right lane closures during concrete pours for the Perham Creek bridge.

Schedule

​Construction began in December 2025 and lasts through late 2026. The project schedule is subject to change.

Details

About

​The work paves the remaining 0.7 miles of trail and builds two new bridges over Perham and Mitchell creeks. Both bridges will be consistent with the historic look and feel that people know and love about the Columbia River Gorge.

Location

N/A |

Historic Columbia River Highway State Trail.

Cost and Funding

​$7.5 million for this phase of the project.

Contractor

​JAL Construction, Inc.

Benefits

​Paving the 0.7 mile gap will complete nearly 10 miles of continuous car-free trail for people walking, biking, and rolling in the Columbia River Gorge between Wyeth State Park and the Mitchell Point Tunnel. To complete this trail segment, we laid the groundwork by finishing the Viento State Park to Mitchell Point project in 2023, which paved the trail from Viento State Park east toward Mitchell Point, and finished the Mitchell Point Tunnel in 2025. More information about our work reconnecting the Historic Columbia Highway State Trail is available in our 2025 Progress Report

Additional Information

​Over the next several years, we have many construction projects planned on I-84 between I-205 and Hood River, and on the Historic Columbia River Highway between Troutdale and Hood River. 

More information.

For Americans with Disabilities Act or Civil Rights Title VI accommodations, translation/ interpretation services, or more information call 503-731-4128, TTY (800) 735-2900 or Oregon Relay Service 7-1-1.

¿Habla ustéd español? Podemos proveer la información en esta publicación en español. Para recibir la información en español, por favor llamé al (503) 731-4128.

Contacts & Media

https://www.oregon.gov/odot/Projects/Project%20Images/Viento-to-Mitchell_Phase2_map.png

Project Contacts

Community Affairs Coordinator
Dee Hidalgo
Email
dee.hidalgo@ODOT.oregon.gov
Phone
503-731-8230

Columbia River Gorge National Scenic Area Coordinator
Terra Lingley
Email
Terra.M.Lingley@odot.oregon.gov
Phone
503-731-8232
Project Hotline
503-489-9057
Project Accommodation Request
503-731-4128

Get Project Alerts

Sign up for the newsletter!

Last Updated

4/3/2026 2:03 PM

Project Number

20677

Project Documents

Related documents to this project
Trail Closure Notice_Perham Creek to Mitchell Point Tunnel March 2026.pdfTrail Closure Notice: Perham Creek to Mitchell Point Tunnel