Traffic Impact
WEEK OF 4/10/4/17:
schedule is subject to change without notice
- The Lower Bridge Way and U.S. 97 intersection will be limited to right-in, right-out turns only during the day. Please follow posted detour signs. The intersection will be fully closed during night hours, Monday through Thursday, from 8:00 p.m. to 6:00 a.m., for paving work.
Access to 11th Street on the north end of Terrebonne remains closed please use Central Ave. On the South end of Terrebonne, access to 11th Street is limited to Smith Rock Way, C Street and Central Avenue.
- The Odem Avenue/ U.S. 97 intersection is open to right in/ right out traffic only. Please follow signed detours.
UPCOMING CLOSURES:
Construction Impacts
PROJECT UPDATE – April 1, 2026
The project remains on schedule and is expected to be completed in October 2026.
In-Town
Construction in town on 11th and C Avenue is progressing well. Crews have completed key upgrades including new water and sewer lines, storm drainage, sidewalks, driveways, ADA ramps, lighting, bus stops, and pedestrian crossings. This week, crews are finishing curbs and driveways. Paving is expected to begin next week. We expect 11th Street (between Smith Rock Way and Central Avenue) and C Avenue to be fully functional by mid-April, with full completion by May 1.
Remaining In-Town Work (April - September):
April 20- June 12
- Rebuild of 11th Street from A Avenue to Smith Rock Way. Full closure of 11th from A Avenue to Smith Rock Way. A Avenue will remain open. Drivers should follow posted detour.
- Rebuild of Smith Rock Way from U.S. 97 to 11th: Full closure of Smith Rock Way from U.S. 97 to 11th Street. Drivers should follow posted detour.
June – September
- Rebuild of Smith Rock Way from 11th Street to 16th Street: Full closure of Smith Rock Way from 11th to 16th Street except for resident access. Drivers should follow posted detour.
- Final paving will occur for the entire job before September 30th. Traffic will be detoured in sections during this time.
U.S. 97
Widening work on the south end of the project is nearing completion. Odem Avenue is expected to fully reopen by April 27, as will Access from U.S. 97 to 11th Street.
Remaining U.S. 97 Work (April - October):
- The full closure of Lower Bridge Way at U.S. 97 will begin on April 27 and will last through project completion. During this time, the entire “dog bone" interchange will be constructed.
- Final paving (top lift) will occur for the entire job before September 30th.
Traffic Impacts on U.S. 97: The highway will remain open throughout the duration of the project, but drivers should expect intermittent lane shifts and closures with flaggers directing traffic. Neighbors in this area should expect intermittent nighttime construction noise.
Thank you for your patience during construction. We appreciate your continued support as we work to improve the community.
*All dates are estimates and subject to change. This website is updated with the most accurate information. You can also sign up for weekly email updates here.
Schedule
Bid Date: May 2, 2024
Construction: Summer 2024- Winter 2026