We are building improvements for the interchange where OR 18 meets OR 219, including the realignment of NE Wynooski Road. We've started Phase 2A construction and anticipate completing construction by 2027.
We are:
- Realigning OR 18 with a new connection to OR 219.
- Adding eastbound exit, westbound entrance ramps and installing new traffic signals at these intersections.
- Adding a bridge carrying the eastbound exit ramp over OR 219.
- Removing the old OR 18 alignment.
- Realigning Wynooski Road to meet the intersection of OR 219 and Wilsonville Road and will install a new traffic signal at the intersection.
- Removing the old Wynooski Road alignment.
- Widening OR 219 for an additional travel lane, sidewalk, ADA ramps and drainage.
Learn about what other work we have planned by visiting the Newberg-Dundee Bypass Phase 2 page.
Past Meetings and Events
Schedule
Estimated Construction: 2025-2027
Location
Multiple
|
OR 219 | Milepost 21.1 to 22.8
OR 18 | Milepost 59.2 to 59.6
Cost and Funding
Right of Way (land purchases) and Construction: $55,876,032