Construction Impacts
Impacts expected the week of April 29, 2024:
Sidewalk curb ramp removal and replacement is expected the week of April 29 at the following locations:
- NE corner of N Richmond Avenue and N Lombard Street
- NW corner of N Richmond Avenue and N Lombard Street
- SW corner of N Mohawk Avenue and N Lombard Street
- SE corner of N Mohawk Avenue and N Lombard Street
- SE corner of N Tyler Avenue and N Lombard Street
- SW corner of N Tyler Avenue and N Lombard Street
- SW corner of N Polk Avenue and N Lombard Street
- SE corner of N Burr Avenue and N Lombard Street
- SE corner of N Alma Avenue and N Lombard Street
- SE corner of N Heppner Avenue and N Lombard Street
- SW corner of N Gilbert Avenue and N Lombard Street
- South side of midblock crossing at Peninsula Crossing Trail and N Lombard Street
- SE corner of N Macrum Avenue and N Lombard Street
- SW corner of N Macrum Avenue and N Lombard Street
- SE corner of N Newell Avenue and N Lombard Street
- SW corner of N Newell Avenue and N Lombard Street
- SE corner of N Westanna Avenue and N Lombard Street
- SW corner of N Westanna Avenue and N Lombard Street
- SE corner of Fortune Aveue and N Lombard Street
- SE corner of McKenna Aveue and N Lombard Street
- SE corner of N Berkeley Aveue and N Lombard Street
Expect daytime lane closures on U.S. 30 Bypass and adjacent side streets and sidewalk closures with pedestrian detours.
This work will cause temporary lane, shoulder and sidewalk closures on U.S. 30 Bypass along North/Northeast Lombard Street, Northeast Killingsworth Street and Northeast Sandy Boulevard and on intersecting local streets. We are providing ADA-accessible pedestrian and bike detours around the work zones and maintaining access for customers of adjacent businesses. Some TriMet bus stops may be temporarily closed or relocated and this will be communicated at the affected bus stops. On-street parking in some areas could be temporarily blocked. We will coordinate with affected property and business owners as needed.
Generally, it takes one to two weeks to complete work on an individual corner, with construction on several corners happening at the same time. However, only one corner per intersection will be impacted at a time.
Work is expected to take place during the day, unless a temporary lane closure on U.S. 30 Bypass is needed. In this case, work may take place at night to minimize traffic impacts.
Schedule
Construction started in March of 2024 and will be completed in the spring of 2025.