OR 229: Fuller and Ojalla Bridges (Siletz River)

Design Phase

Region 2: Willamette Valley and Northwest Oregon (Siletz, Lincoln)


​​​​​​​​​​​We're working on the Fuller and Ojalla Bridges over the Siletz River to make repairs in order to maintain and preserve the bridges.​


Banner image: Designing a Modern Transportation System and Investing in Oregon’s Future.

Details

About

Enlarged Project Area MapThe existing coatings on the Fuller and Ojalla Bridges need to be replaced to help prevent damage over time. 
 
To help protect and preserve the bridges, we're:
  • Removing lead paint and asbestos if needed.
  • Removing rust.
  • Replacing the rivets, joints and bearings if needed.​
  • Painting the steel supports and handrails.
  • Making minor repairs to the sidewalks.
We're planning to build and will have a better idea about the construction schedule and cost as we get further into design. 

Schedule

Design: 2024 - 2026
Construction: 2027​ - 2028

Location

OR 229 |

​Fuller Bridge | Milepost 23.1
Ojalla Bridge | Milepost 20.7

Cost and Funding

Design and construction: $11,656,813​

​Pedestrians, including those with disabilities, will have access through or around the work zone.

Contacts & Media

Project Area Map

Project Contacts

Transportation Project Manager
Charles Stouder
Email
charles.stouder@odot.oregon.gov
Phone
503-302-3874

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

12/31/2025 11:39 AM

Project Number

23123