Overview and construction impacts
Construction is underway on
OR 217 and surrounding streets!
¡La construcción ha comenzado
en OR 217 y calles cercanas!
Para información en español, visite
This project will improve safety and reduce bottlenecks on OR 217 by adding auxiliary lanes, or ramp to ramp connections, between Beaverton-Hillsdale Highway and OR 99W. Work began in December 2021 and remains on schedule to be completed by the end of 2025. In partnership with the City of Beaverton and Washington County, the project also includes targeted improvements to local bicycle and pedestrian routes.
With a lot of patience, we’ll all get through construction together and benefit from a safer and more reliable highway.
Current Impacts
As of 12/10/2024
Hall Boulevard overpass in Tigard closed until early 2025.
New highway impacts
- Overnight and daytime single lane closures on northbound and southbound OR 217 between Denney Road and OR 99W to restripe the lanes and install reflective pavement markers on the highway.
- Overnight on 12/10 between 8 p.m. and 5 a.m.
- During the day on 12/11 between 10 a.m. and 3 p.m.
- Nighttime single lane closures on northbound and southbound OR 217 in various sections of the project area 12/11-12/13.
New local road impacts:
- No new impacts anticipated this week.
Ongoing construction impacts: - Overpass impacts:
- The Hall Boulevard overpass over OR 217 near OR 99W and Pfaffle Street in Tigard is closed until early 2025. The overpass is being rebuilt with wider footings to make room for the new auxiliary lanes and shoulders underneath on OR 217. People walking, rolling and bicycling will continue to have access across OR 217. More information is available on our Hall Boulevard Overpass Replacement page.
- Pedestrian impacts:
- The Hall Boulevard overpass over OR 217 near OR 99W and Pfaffle Street in Tigard is closed until early 2025. People walking, rolling and bicycling have access across OR 217 throughout the closure using a temporary bicycle and pedestrian bridge.
- General impacts:
- Intermittent closures of existing auxiliary lanes and shoulders on OR 217 and nearby local roads throughout the project area. Various on- and off-ramps are narrower, but will remain open, unless stated otherwise.
- Intermittent nighttime work throughout the project area. We have a 24/7 noise hotline for night noise concerns: (503) 412-2349.
- Crews are transporting dirt and materials from the project area to a site on ODOT property at the I-5 and I-205 interchange. Crews are also staging dirt and materials near SW Denney Road and SW 105th Avenue. Some materials are delivered at night and nearby neighbors may hear some noise.
Ongoing impacts from other construction projects in the area:
- Our OR 99W paving project currently in construction will pave, build new sidewalks and bicycle lanes, upgrade sidewalk curb ramps, repair bridges, and make safety improvements on OR 99W between I-5 and McDonald Street.
- Willamette Water Supply is updating pipelines in the OR 217 project area. Please check the Metzger Pipeline East project website for the most up-to-date information about traffic impacts.
Safety reminders!
- Please be respectful of construction crews working in the project area. Objects thrown out of vehicles are dangerous to workers. Slow down and be mindful of work zones to keep crews and highway users safe.
- Keep in mind that traffic lanes have shifted in several areas throughout the project. Pay close attention to new barriers and markings on the road.
- Slow down, especially at night. A reduced speed limit of 45 MPH is in effect in work zones. There is also increased speed enforcement throughout the corridor.
Stay informed about construction
- Visit this website during construction, we'll update information here regularly.
- Sign up for construction email updates to learn about major traffic impacts and periodic progress updates.
- Check TripCheck.com for up-to-date traffic impacts during construction.
- Share questions or concerns with the project team via email at hwy217@odot.oregon.gov or phone at 503-265-8704.
Overview of Construction Impacts
We know construction can be disruptive for travelers and local residents.
Much of the work on OR 217 will take place at night when traffic volumes are lower. However, daytime work is unavoidable and we anticipate more traffic and congestion in the area during construction.
Construction is dynamic and some of these impacts may change as the project progresses.
We will work to keep you informed throughout the project and minimize construction impacts to the community as much as possible. Some of the considerations the project team will take include:
- Reducing or limiting work during some holidays and cultural festivals.
- Providing as much notice as possible before any closures.
- Dedicating additional time to translate important construction notices.
What You Can Expect During Construction
Impacts are listed by categories below. Use the plus signs to expand each section. Click again to minimize.
For Drivers
- Lane closures will routinely occur at night between 9 p.m. and 5 a.m.
- Full closure of one direction of OR 217 at a time for up to five weekends.
- Short-term closures of existing auxiliary lanes.
- Highway ramp closures will routinely occur at night between 9 p.m. and 5 a.m.
- Allen Boulevard: up to four-month closure of the left turn from Allen Boulevard to OR 217 south (COMPLETE).
- Denny Road: up to five-month closure of the southbound on- and off-ramps during construction of the new frontage road (COMPLETE).
- Hall Boulevard: up to two-month closure of the on-ramp to OR 217 south (COMPLETE).
- OR 99W: up to two-month closure of the on-ramp from northbound OR 99W to OR 217 northbound (COMPLETE).
- Other OR 217 on- and off-ramp closures for up to a few days
Lane closures and some nighttime full closures on local roads adjacent to OR 217 including Hall Boulevard, Allen Boulevard, Denney Road, Scholls Ferry Road, Greenburg Road and OR 99W.
Approximately nine-month closure of the Hall Boulevard overpass between OR 99W and Pfaffle Street in Tigard to motor vehicles (IN PROGRESS – expected completion in early 2025).
For People Biking, Walking, Rolling or Taking Transit
- A temporary bicycle and pedestrian bridge is available for non-motorized use while the Hall Boulevard overpass in Tigard is closed.
- OR 217 shoulders are closed to people on bikes for the duration of the project.
- People biking on local streets in the project area are being directed to ride in the travel lane or use a different route due to short-term shoulder or lane closures.
- Pedestrians on local streets in the project area may encounter sidewalk closures, in which case signed ADA-accessible detour routes will be posted.
- There are impacts to bus stops and routes during the rebuilding of the Hall Boulevard Overpass. Look for more information at the bus stops and on Trimet.org. The WES Commuter Rail will be unaffected during construction.
For Nearby Residents and Businesses
Nighttime work is needed to minimize traffic impacts. When crews are working nearby, residents and businesses may hear construction noise and feel vibrations. Call our 24/7 noise hotline (503-412-2349) to reach a person to discuss nighttime noise concerns.
When crews are working nearby at night residents may notice light in the construction zones.
Crews removed trees and vegetation along OR 217 on ODOT property at the start of construction. We will plant native trees and shrubs in targeted areas throughout the project area as construction wraps up.
Tips for Traveling Safely in Work Zones
- Orange is your cue! Pay attention when you see orange signs, barrels, cones and barricades.
- Obey all speed signs. Speeds will be reduced on OR 217 and Scholls Ferry Road for your safety and the safety of others.
- Expect delays — plan for them — and leave early so you can drive safely through the work zone.