Project summary
Construction of a traffic circle at the intersection of Eagle Creek and River Mill Roads in the City of Estacada (Clackamas County) to allow a continuous flow of traffic from an evacuation during emergencies or power outages.
Project budget: $797,913.00
Project Phase: Design
Awardee: City of Estacada
Project timeline
- 04/01/2026 - Complete engineering
- 11/01/2026 - Environmental clearance
- 12/30/2026 - Sealed bid procurement
- 06/01/2027 - Mobilization
- 10/31/2027 - Construction complete
- 02/02/2028 - Project closeout