Architectural Index: Construction Cost Estimating

The Architectural Index consists of a series of loosely related policy ‘modules’ that provide detailed policy related support to the Oregon Housing and Community Services (OHCS) Architectural Standards a (OAS) and other department guidance. These architectural standards and guidance apply to all projects going through the Oregon Centralized Application (ORCA) process.

Last updated: June 2026, Version 1


Module 04.01 Construction Cost Estimating

04.01-01 Overview

When a construction cost estimate is required by the department it must meet one of the three types of criteria detailed below. Which type of criteria to be used in preparing the estimate is defined in the department issued request for a cost estimate i.e. a required task issued to the funding program participant via their project specific WorkCenter. Where the type of criteria to be used is not identified, the Type I Criteria must be used as a default unless the Type II Criteria or the Type III Criteria has been approved in writing by the department.

04.01-02 Type I Estimate

(3rd Party Construction Cost Estimate)

Criteria for this type of construction cost estimate are as follows:

  • Cost Estimator Qualifications:
    • Each key individual participating in the estimating services (estimator) must have at least four years of experience providing commercial and/or multifamily residential construction estimates.
    • The estimator must have demonstrable familiarity with the current construction cost environment in the State of Oregon.
    • Identity of Interest: The individuals providing cost estimating services, and their firms, must not have an identity of interest with the project owner, the owner’s property, or any management entity for the property and further must not provide other services (services outside the scope of cost estimate service, e.g. architectural design, construction, etc.) on the same project. If any pending litigation or claims exist against any of the involved firms or individuals related to their professional service (either as the primary consultant or as sub-consultant), these must be disclosed in writing to the project owner and to OHCS prior to engagement of services.
  • Cost Estimate Format and Content Requirements
    • Estimate age: The estimate must have been completed or updated by the cost estimator within 45 days of submission to the department.
    • Standard to be followed: The estimate must follow standard industry practices for level of completeness, detail, and content. CSI MasterFormat or UniFormat II structure for the estimate may be used.
    • Statement of estimate conformity with department requirements: The estimate must contain a statement in the estimate introduction that specifically states that the estimate conforms to the requirements of this module.
    • Professional profile: The estimate must include a profile section that, at a minimum, includes the following information:
      • Description of the estimator’s firm including size, primary clientele, and services offered.
      • A brief resume/professional bio that includes all professional licenses/certificates held by key personnel and each individual’s number of years of construction cost estimating experience.
      • References: Provide a list of at least three prior construction estimating jobs similar in size and complexity to the project that current services are being requested/provided for. Include the names of the individuals for whom the estimates were conducted, the name
        of their organization, and a contact phone number for each reference.
    • Estimate scope and documents relied upon: The estimate must identify and briefly describe the design documents and any other project related documentation that was used to formulate the estimate. Description of the design documents used must include the estimator’s assessment of the estimated level of completeness of the documents given in a percent complete figure and must include the date of the subject documents.
    • Cost data references: The estimate must indicate what cost data references were used and how costs were derived.
    • Estimate accuracy: The estimate must identify any limitations to the estimate’s accuracy including any undefined ‘knowns’ and any cost escalation risks that the estimator may be aware of based on the documentation provided to them and on their experience with similar projects.
    • Site costs: Provide a section of the estimate dedicated to site costs with a site related sub-total.
    • Other itemized costs: Provide itemized cost figures for the following:
      • General Conditions
      • General Overhead
      • Profit
      • Construction Contingency
    • Escalation: The estimate must include an escalation figure showing projected cost at the projected construction start date. The projected construction cost date must be indicated in the estimate.
    • Estimate contingency: The estimate must include an estimate contingency section that, as a whole, describes how well the project has been defined at the time the estimate is made (this is not intended to be a construction contingency (set-aside for unforeseen costs once construction commences). The estimate contingency section must, at a minimum, include the following general components:
      • Generally list and/or describe any aspects of the project where there is high probability that a project cost exists but the source or driver of that cost has not yet been defined in the design documents.
      • Provide an estimate contingency in the form of a percent figure. This percentage is intended to capture project costs that will occur or are likely to occur based on the item above.
      • Provide an assessment of the cost estimate’s accuracy in terms of a percentage figure (this is different from the percentage figure provided under the item above. This percentage figure represents how far the final construction cost may vary from the subject cost estimate.

04.01-03 Type II Estimate

(Project Team Construction Cost Estimate)

Criteria for this type of construction cost estimate are as follows:

  • Type II Criteria are identical to Type I Criteria with the following exceptions:
    • 04.01-02 Type I Estimate, 1) Cost Estimator Qualifications, c); Identity of Interest:
      This exception means that the Type II Criteria estimate may be developed by any individual deemed by the project owner to have the expertise and experience necessary to provide cost estimating services sufficient to develop an accurate budget setting figur e for the construction of the project. The selected cost estimator must, however, still meet the qualifications required by 04.01-02 Type I Estimate, 1) Cost Estimator Qualifications, a) and b).
    • 04.01-02 Type I Estimate, 2) Cost Estimate Format and Content Requirements, d) ; Professional Profile

04.01-04 Type III Estimate

(Combined Rehabilitation Scope of Work and Construction Cost Estimate)

Criteria for development of this document is as follows:

  • Type III criteria are identical to Type I criteria with the following exceptions and additions:
    Exceptions:
    • 04.01-02 Type I Estimate, 1) Cost estimator qualifications, c) Identity of interest: See additional information on this exception under Section P.1.02b, a).
    • 04.01-02 Type I Estimate, 2) Cost estimate format and content requirements, b) Standard to be followed
    • 04.01-02 Type I Estimate, 2) Cost estimate format and content requirements, d) Professional profile

Additions:

  • Standard to be followed for Type III criteria (Combined SOW/cost estimate):
    • The combined SOW/cost estimate must be combined into a single document that directly relates scope items to their respective cost.
    • A method of presenting costs in ‘elemental’ or functional categories such as that characteristic of the CSI UniFormat II (not to be confused with “MasterFormat”) method is required. This places descriptive emphasis on the functional or physical scope
      attributes of the project and less on the physical materials used.
    • The combined SOW/cost estimate must describe and provide costs for all significant systems and assemblies that make up the full proposed scope of the project. Note: The combined SOW/ cost estimate is separate from (a different document from) the ‘Opinion of Costs’ provided in the CNA.
    • The combined SOW/cost estimate must separate the proposed scope into two clearly distinguishable categories as follows:
      • SOW items that are identified in the CNA as falling within the immediate and/or 2 -year needs category and,
      • SOW items that are not identified as immediate or two -year needs in the CNA but the project owner has identified as being a necessary or prudent part of the rehabilitation scope.
    • The combined SOW/cost estimate document must be developed by an individual or entity that is unaffiliated with the individuals and/or the organization that has or will be providing CNA services on the same project.
    • The primary individual who has prepared the document and the name of their organization must be clearly identified in the document.