Module 05.01 Construction Phase Engagement Requirements
05.01-01 Overview
The Construction Phase Submission Requirements give the department a critical view into the project in two fundamental ways:
- Documents and communications: By providing access to certain critical construction administration related documents and including the department in high -level project management communications, and;
- Construction site access: By providing physical access to the construction site such that the department can periodically observe construction activity and progress.
The Construction Phase of the project begins when construction activity commences.
05.01-02 Project status updates
Project status updates refer, as a whole, to the Construction Administration (CA) related documents and communications that are required to be sent to the department over the course of the project’s construction phase.
-
Required Documents and Communications
In general, the required documents are the same as those that are routinely transmitted to key members of the owner’s project team and other key project stakeholders. The list of documents given below may be modified with written approval given by the department on a case-by-case basis. Adequate rational for the modification must be provided in writing by the owner’s project team. The department may, on a case-by-case basis, request submission of documents that are not listed below. - Contractor’s application for payment: Forms AIA G702 (must be signed by the project architect) and AIA G703 (a non -AIA G703 equivalent with similar formatting is acceptable)
- Construction site meeting minutes
- Project architect’s construction observation reports
- Observation reports prepared by sub-consultants to the project architect
- Special Inspection Reports (as applicable)
- Project schedule updates
- Change Order Request (COR) and Change Order (CO) log
-
All Change Order Requests (COR)s (CORs must be issued to the department for review prior to project owner approval).
Note regarding change orders: The department must be notified prior to owner approval of the COR. Though department approval of CORs is not required, the department maintains the authority to disapprove the use of program funding on COR line items when the department deems the request to be outside of its expectations for the project. Any department disapproval of CORs will be issued in writing to the owner’s development team.
-
Owner and/or development team knowledge of, or communications regarding, a significant unforeseen project development or issue. Also see item 4) under this section.
-
Other documents: As deemed necessary or prudent by the department and as requested.
-
Timing of project status updates
Except for documents and communications that fall under item 1); i) and j) above, submit Required Documents and Communications listed under item 1) above to the department at the same time they are routinely provided to other key members of the owner’s project team and other key project stakeholders. Typically, monthly submittals of project status updates are sufficient unless substantive changes or events such as those falling under item 1), i) under this section and under section 05.01-03 Emergent Issue and Project Change Related Communications require more frequent communication as a means of keeping the department apprised of important project related developments.
Submit Project Status Update packages per instructions in the project’s OHCS WorkCenter. -
Owner’s project team response to department comments/questions
The department may issue questions or comments to the owner’s project team regarding the information provided. The project team is expected to work diligently with the department to resolve any issues or concerns that may be expressed by the department stemming from its review of Project Status Updates. -
Highlighting important construction related issues
When Project Status Update Submissions consist of documents that contain information regarding important project developments/issues/concerns, the owner’s project team must also send an email sent directly to the OHCS Construction Manager specifically apprising the department of the development. -
Department response to Project Status Updates
Unless the status update includes information that has been specifically called out as an issue needing attention or conspicuously identifying or suggesting that a reply is expected, the department will typically not formally respond to routine, periodic updates from the owner’s development team.
05.01-03 Emergent Issue and Project Change Related Communications
The department requires the owners project team to promptly and directly notify the OHCS Construction Manager when either of the following occur:
-
Change Order Requests (COR) where the proposed cost of a single item in the request is $10,000 or more. The department must be notified prior to owner approval of the COR.
-
Significant Emergent Issues when the issue can reasonably be considered substantive to a primary project stakeholder such as OHCS. In such cases, the owner’s project team will keep the department apprised in a timely manner of the issue’s development and the process by which it is being resolved. Periodic and timely reporting on the status of the issue by the owner’s project team will continue until the issue is fully resolved to the satisfaction of the department.
05.01-04 Department Construction Phase Site Visits and Construction Observation
This section defines the department’s construction site access related actions and expectations.
-
OHCS Construction Observation Site Visits
At its discretion, the department may conduct one or more Construction Observation visits to the project site during the construction period to determine if the project is being executed in accordance with funding program requirements and expectations. The frequency of site visits and the degree of related project team contact is based on a number project characteristics including, but not limited to, project complexity and applicable funding program requirements. -
OHCS Construction Administration Consultant (CA -Consultant)
-
Role of the Department’s CA -Consultant
At its discretion, the department may engage a CA -Consultant to assist with construction phase project site visits to observe the construction work. The CA -Consultant is engaged by the department to inform the department on matters of construction progress, quality of workmanship, and general conformance with the department’s funding-related conditions. The role of the department’s CA -Consultant
does not include providing guidance of any kind to the owner’s project team. Further, the department’s CA-Consultant will not be engaging with the project team in a formal inspection or enforcement related capacity. -
Communications between the CA-Consultant and the project team
Some direct communication between the CA -Consultant and the project team is necessary and expected, however care must be taken by both the CA-Consultant and the project team to keep communication within the expected guidelines of the department. The following general communication guidelines must be understood and followed by both parties: - General: The OHCS CA -Consultant is under contract with the department to provide Construction Administration support to OHCS only. Any communication regarding the technical aspects of design or construction that may come directly from the CA -Consultant to the project team is strictly unofficial and does not represent the will or the position of the department. Any official communication from the department regarding the project will be issued in writing directly to the project team by department staff.
- Construction observation reports: Construction observation reports that have been generated by the CA -Consultant are for use by the department only. The department may, at its sole discretion, decide to share the CA -Consultant’s observation reports with the project team so it has the opportunity to determine if information in the report can be used to benefit the project. When CA-Consultant Observation reports are shared with the project team the following condition applies:
- Construction Observation reports written by the department’s CA-Consultants may include suggestions or direction on how the design or the construction of the project could be improved. All such suggestions and direction are to be regarded as the personal opinion of the CA -Consultant and
do not represent the opinion of the department.
- Regardless of the manner in which such opinions are conveyed in the CA -Consultant’s reports, the project team is in no way to construe such opinions as de facto improvements to the observed condition, nor as directives from the department, nor as presumptions on the part of the department that such opinions will be followed by the project team.
- Any use of the information in the CA -Consultant’s Construction Observation Reports by the project team is entirely voluntary and must first be independently deemed by the legally responsible entities who control the design and construction work being performed to be the most prudent approach to be taken.
-
Responding to department requests
Based on observations made during site visits by department personnel or a department engaged CA-Consultant, the department may suggest or require clarifications or revisions to the construction documents. The project owner and their project team are obligated by their acceptance of funding from one or more department administered programs to energetically engage with the department in reaching satisfactory resolution to any issues or concerns that may be expressed by the department. Failure to reach satisfactory resolution of department identified issues or concerns may lead to project schedule delays and may jeopardize project funding from the department.
05.01-05 Completion Phase Requirements
(Reserved for future updates to architectural standards)