Architectural Index: Rehabilitation Scope of Work

The Architectural Index consists of a series of loosely related policy ‘modules’ that provide detailed policy related support to the Oregon Housing and Community Services (OHCS) Architectural Standards a (OAS) and other department guidance. These architectural standards and guidance apply to all projects going through the Oregon Centralized Application (ORCA) process.

Last updated: June 2026, Version 1


Module 03.02 Rehabilitation Scope of Work

03.02-01 Overview

When work is planned to an existing structure and when a Rehabilitation Scope of Work is required by the department, the scope of work must, at a minimum, comply with the provisions of this Architectural Index module.

03.02-02 Scope of Work (SOW) Requirements

Prepare a written Scope of Work (SOW) that addresses all items listed in this section.

  • General Information
    • Date of the SOW
    • Project Name
    • The primary individual who has developed the SOW, their position title, and the name of their organization.
    • The primary individual who has developed the required Cost Estimate portion of the SOW, their position title, and the name of their organization.
    • Important notes: The SOW must be developed by an individual or entity that is not affiliated with the individuals and/or organization that has or will be providing CNA services on the same project. It is recommended that the architect that will be preparing the construction documents for the project be engaged to develop the SOW and coordinate that work with the section 03.02-3 Cost Estimate Requirements.
  • Executive Summary
    Provide a brief overview of the scope of the proposed project including a brief rationale for the proposed scope of work. This can be a duplicate statement from the ORCA application however care should be taken to ensure this statement succinctly and accurately captures the project’s general character, scope and intent.
  • SOW Elements List
    • List and describe each of the major elements of the project by major system or body of work i.e. foundation, building envelope, roof, dwelling unit interiors, site, plumbing etc. This list should be detailed and comprehensive enough to clearly convey to a third party the full scope of the project. Major areas of work can be titled in a way that describes their general purpose like, “envelope replacement” but they must also go further than this by providing a reasonable level of related detail of the sy stem elements affected. For example, the primary building components that will be repaired or replaced should be listed and the scope of work to each item briefly described. In the current “envelope replacement” example, sheathing, siding, windows, water resistive barrier, rainscreen, etc. should be itemized as applicable and the scope of the work related to each item briefly described.
    • Separate the proposed scope of work list into three categories:
      • Category A: Imminent Health & Safety Needs as identified in the project’s CNA; All needs identified as “imminent health and safety” should be included in Category A of the SOW. Imminent health and safety issues are those that pose an immediate and serious threat to health and safety. The department may require that Category A items be addressed to the satisfaction of the department before considering or approving a funding request.
      • Category B: Critical needs as identified in the project’s CNA; Critical Needs, for the purpose of the Architectural Index, are those that fall within a two-year needs window and are not already included in Category A (the Immanent Health and Safety Needs category).

        It is assumed that all needs identified as “critical” will be included in Category B of the SOW. If the funding applicant deems an item to be incorrectly categorized as such by the CNA provider, the item must still be listed in Category B but must be clearly identified in this list and conspicuously noted as “not deemed to be a Category B item by the project owner.”

        Items that are not identified in the CNA as being a Critical Need must not be included in the Category B part of the SOW.
      • Category C: Renewal Needs
        Defined as physical needs identified in the CNA that fall beyond the two-year needs window, and the project owner has determined are a necessary part of the project scope. Include a Category C in the SOW Elements List even if there are no items that fall in this category. If no items fall in this category, state “none” or “no items.”
      • Category D: Owner Identified Needs
        Defined as physical needs that are supplemental to what has been identified in the project’s CNA – these are items that are not identified in the CNA.

        Category C and D are applicable only when the project owner is proposing scope of work items not within the immediate to two-year needs window per the project’s CNA. Include a Category D in the SOW Elements List even if there are no items that fall in this category. If no items fall in this category, state “none” or “no items”.
  • Rational for Renewal and Owner Identified Needs
    • When project scope items are listed in Categories C and D under item 3), b ), provide a written rational for why the proposed work should be considered for funding.
  • Rational for Significant CNA and SOW Cost Value Differences
    • When project costs between the values given in the CNA and the SOW vary significantly, provide an explanation or rational for the variation.

03.02-03 Cost Estimate Requirements

Prepare a companion cost estimate based on the SOW developed per Scope of Work section. The cost estimate must address all items listed below.

  • Intent
    • The cost estimate must be developed so it is directly and easily relatable to the SOW. This means that costs must be broken down to correspond directly with the SOW Elements List developed per Scope of Work, SOW Elements List section. The manner that scope and cost information is conveyed is up to the preparer, but it must meet the intent of this section.
    • Estimator Qualifications:
      The estimator (individual principally responsible for the estimate) must have at least four (4) years of experience providing commercial and/or multifamily residential construction estimates and; The estimator must have demonstrable familiarity with the current construction cost environment in the State of Oregon.
  • Documents and information relied on
    The estimate must identify and briefly describe the design documents or other information that was used to formulate the estimate.
  • Cost data references
    The estimate must indicate what cost data references were used and how costs were derived.
  • Estimate limitations
    The estimate must identify any limitations to the estimate’s accuracy including any undefined ‘knowns’ and any cost escalation risks that the estimator may be aware of based on the documentation provided to them and on their experience with similar projects.
  • Itemized costs:
    • Separate from the costs that are itemized to correspond with the SOW list of needs, provide itemized cost figures for the following:
      • General Conditions
      • Overhead
      • Profit
      • General contractor’s construction period contingency (If included. State “none” if not included).
    • If the party that prepared the cost figures has a Schedule of Values or cost estimate format that they normally provide to communicate costs, provide the document as an appended attachment to the SOW. If included with the SOW, this document is not a substitute for providing costs in the SOW in the format as outlined in this Architectural Index module.
  • Escalation
    The cost estimate must show costs that include escalation tied to a presumed construction start date (or construction phase mid-point). Include the date used for calculating escalation and identify what point in the construction phase (construction start/mid-point) the date represents. Show a percent figure that was used to adjust current day costs to arrive at the escalated figure.