Operating/Under Review. The facility commenced commercial operation of 200 MW of wind power generation components on June 27, 2025. The certificate holder has authorization to construct an additional 100 MW of wind power generation facility components and must complete remaining construction by June 2028.
On July 2, 2026, the Department issued its Proposed Order on RFA2 and on the same date issued a Public Notice requesting comments on the Proposed Order on RFA2. The Department is accepting comments on RFA2 and the Proposed Order on RFA2 from July 2 through July 31, 2026. The Proposed Order recommends approval of RFA2 subject to existing, amended and new site certificate conditions.
The Public Hearing on the Proposed Order was held on July 24, 2026 at the Oregon Department of Energy office in Salem, Oregon. Following completion of the comment process on September 14, 2026, the Department continued its review of issues raised in comments received. On November 18, 2026, the Department issued its draft Final Order on RFA2, including changes recommended in response to issues raised. The draft Final Order on RFA2 will be reviewed by the Energy Facility Siting Council at the November 20 and December 18, 2026 meeting.