Skip to main content

Oregon State Flag An official website of the State of Oregon »

EFSC Project Updates: November 2026

oregon-shape-image This page has the latest information on energy projects under state jurisdiction. We update this page monthly to help you stay involved and in-the-know about energy facility news.
November 2026 Siting Project Updates

The Latest Updates
Approved Facilities Under Construction:
Biglow Canyon WindFarm – preliminary Request for Amendment #5

The Department received the pRFA on October 19 and issued Public Notice of receipt of the pRFA on October 27, 2026. The Department is initiating review and coordination with reviewing agencies, and will identify additional information needed from the certificate holder in November.

Big River Energy Facility  – Notice of Intent

The Department accepted comments on the NOI through September 25, 2026, and is continuing to coordinate with reviewing agencies to help inform the requirements to be included in the Project Order. The Project Order will be issued in November 2026.

Boardman Coal Plant – Review of Termination Request

The Department received a concurrence letter from the Oregon Department of Environmental Quality confirming that results of groundwater monitoring at the site were adequate. The Department will present its recommendations to Council for concurrence, modification, or rejection to terminate the site certificate, at the November meeting.

Buckley Solar Facility – Notice of Intent

The pASC must be submitted by August 17, 2027.

Carty Generating Station – preliminary Request for Amendment #4

The Department deemed RFA4 complete and issued a Proposed Order on Request for Site Certificate Amendment 4 on October 30, 2026.

The Department will accept comments on the Proposed Order on RFA4 from October 30 through December 14. A public hearing will be conducted by EFSC on November 19, 2026, with opportunities for public participation in person at the Port of Morrow Riverfront Room and online/via phone. Additional details are provided in the public notice available on the Department’s webpage for the project.

Cascade Renewable Transmission System – Preliminary Application for Site Certificate (pASC)

The Department is drafting the Draft Proposed Order and coordinating with reviewing agencies on review of the pASC. Completeness review will continue through Q4 2026.

Deschutes Solar and Battery Energy Storage System (BESS) Facility  – Preliminary Application for Site Certificate (pASC)

The Department is drafting the Draft Proposed Order and coordinating with reviewing agencies on review of the pASC. Completeness review will continue through Q4 2026.

Heppner Wind Project – Notice of Intent

The preliminary Application for Site Certificate must be submitted by March 27, 2027.

Klamath Cogeneration Project preliminary Request for Amendment #6 – Proposed Order

The comment period on RFA6 and the Proposed Order on RFA6 closed on August 28, 2026. The Department and the certificate holder provided responses to comments on September 2 and August 28, 2026, respectively. The Department anticipates issuing the draft Final Order and Notice of Draft Final Order, evaluating the issues raised during the comment period in November 2026.

Klamath Falls Energy Center – Notice of Intent

The preliminary Application for Site Certificate must be submitted by December 2027.

Muddy Creek Energy Park – preliminary Application for Site Certificate (pASC)

The Department is drafting the Draft Proposed Order and coordinating with reviewing agencies on review of the pASC. Completeness review will continue through Q4 2026.

Nolin Hills Wind Power Project – preliminary Request for Amendment #1 (on Hold)

The certificate holder requested until January 2027 to response to the Department’s data request. The Department has agreed to put the amendment on hold until the certificate holder is able to respond to its data request.

Saddle Butte Energy Facility – Notice of Intent Withdrawn

On October 23, 2026, the applicant notified the Department of its withdrawal of the NOI. 
The Department removed the project from EFSC/ODOE review queue and updated the project status on its webpage in early November.

Speedway Energy Facility – Notice of Intent

The Department issued its determination that the pASC was incomplete on September 17, 2026.
The Department requested that the certificate holder respond to its data request by November 17, 2026.

Sunrise Solar and Storage Projects – Notice of Intent

The preliminary Application for Site Certificate must be submitted by February 27, 2027.

Umatilla-Morrow County Connect Project – Preliminary Application for Site Certificate (pASC) 

The Department received revised exhibits in October 2026. The Department is continuing to review the pASC and drafting of the Draft Proposed Order.

Wagon Trail SolarFacility – preliminary Request for Amendment #1

The Department issued Public Notice of Receipt of the pRFA on November 3, 2026. The Department is initiating review and coordination with reviewing agencies, and will identify additional information needed from the certificate holder in November.

Wheatridge Renewable Energy Facility East Request for Amendment #2 – Proposed Order

The Department anticipates issuing the draft Final Order and Notice of Draft Final Order, evaluating the issues raised during the comment period in November 2026.

Rulemaking - Compliance Rulemaking

Council consideration and possible adoption of the rules are scheduled for the November 19–20, 2026 meeting.

Rulemaking - Financial Expertise and Retirement Assurance

Staff is preparing a report summarizing the Rulemaking Advisory Committee (RAC) process, stakeholder feedback, and options for strengthening information requirements while addressing disclosure, timing, and administrative burdens.

Staff plans to seek Council policy direction at the November 19–20, 2026 meeting. That direction will guide revised draft rules for RAC review before staff returns to Council to request initiation of formal rulemaking.

Rulemaking - Carbon Monetary Offset

Council consideration and possible adoption of the rules are scheduled for the November 19–20, 2026 meeting.


Shepherds Flat North with Truck.jpg