Applegate Valley Fire Station 51 Expansion

Project Summary

The station's expansion will make sure critical firefighting resources are properly housed and maintained. The project will expand the station's conference and training room, creating a more functional space for firefighter training, incident management, local organizations, and public gatherings. This will strengthen both emergency preparedness and community engagement.

Project Budget: $613,000.00

Project Phase: Design

Awardee: Applegate Valley Rural Fire District # 9

Project Timeline

  • 11/30/2025 - Project manager recruitment & hiring
  • 02/28/2026 - Environmental clearance
  • 04/30/2026 - Permitting & pre-construction coordination
  • 06/30/2026 - Design & engineering finalization
  • 08/31/2026 - Procurement / bidding
  • 09/30/2026 - Contract award and mobilization
  • 09/30/2027 - Construction phase
  • 10/31/2027 - Final inspection and punch list
  • 12/31/2027 - Project closeout and reporting