Project Summary
The station's expansion will make sure critical firefighting resources are properly housed and maintained. The project will expand the station's conference and training room, creating a more functional space for firefighter training, incident management, local organizations, and public gatherings. This will strengthen both emergency preparedness and community engagement.
Project Budget: $613,000.00
Project Phase: Design
Awardee: Applegate Valley Rural Fire District # 9
Project Timeline
- 11/30/2025 - Project manager recruitment & hiring
- 02/28/2026 - Environmental clearance
- 04/30/2026 - Permitting & pre-construction coordination
- 06/30/2026 - Design & engineering finalization
- 08/31/2026 - Procurement / bidding
- 09/30/2026 - Contract award and mobilization
- 09/30/2027 - Construction phase
- 10/31/2027 - Final inspection and punch list
- 12/31/2027 - Project closeout and reporting
Contact
Tallie Jackson, Administration Chief
Phone: 541-899-1050
Email:
tjackson@applegatefd.com