Project summary
This project supports the City of Phoenix to construct four new parking lots with stormwater management facilities. The project aims to revitalize the downtown core of Phoenix by supporting existing businesses and attracting new development.
Project Budget: $4,143,655.00
Project Phase: Design
Awardee: City of Phoenix
Project timeline
- 01/30/2025 - Delivery of onboarding documents
- 03/31/2025 - Procure engineering firm
- 06/15/2026 - Environmental clearance
- 06/30/2026 - Final design
- 06/30/2026 - Permitting
- 07/31/2026 - Land acquisition
- 07/31/2026 - Construction procurement
- 09/30/2026 - Construction start
- 06/30/2027 - Construction completion
- 06/30/2028 - Project closeout
Contact
Zac Moody, Community Development Director
Phone: 541-535-2050 Ext. 313
Email:
zac.moody@phoenixoregon.gov