Project summary
This project will install a single permanent generator at the Water Treatment Plant, as well as install transfer switches at the river intake, and two booster pump stations (three transfer switches in total). The project includes constructing a new intake structure to address health and safety concerns and provide for future expansion of the intake pumps.
Project budget: $1,012,776.25
Project phase: Design
Awardee: Glide Water Association
Project timeline
- 05/01/2025 - Procure engineering firm
- 10/01/2025 - Complete final design
- 05/01/2026 - Obtain federal/state agency approvals
- 05/01/2026 - Environmental clearance
- 05/01/2026 - Advertise for construction bids
- 05/01/2026 - Bid opening
- 06/01/2026 - Construction begins
- 11/01/2026 - Construction completion
- 11/01/2026 - Project closeout