The Emissions Inventory provides information on all the Toxic Air Contaminant emissions from a facility, and includes information on a facility’s operations and activities, as well as fuel and material usage rates. This is often the longest step in the CAO risk assessment process as DEQ needs to verify that all activities have been accounted for, and that the most representative emissions data available are used. In some cases, DEQ will require a facility to perform source testing at this stage if insufficient data is available to estimate emissions.
For an introduction to emissions inventories and why they matter, please see EPA's Fact Sheet. An Emissions Inventory is a list of each toxic air contaminant regulated under the Cleaner Air Oregon rules that a facility emits in a given year. The Emissions Inventory includes the amount of each toxic air contaminant emitted from each individual emissions-producing activity.
Aug. 13, 2020: DEQ calls Covanta Marion, Inc. into the program.
Oct. 26, 2020: Facility submitted Emissions Inventory extension request.
Nov. 10, 2020: DEQ responded to Emissions Inventory extension request.
Nov, 24, 2020: Facility submitted Emissions Inventory.
March 11, 2021: DEQ responded to Nov. 24, 2020 Emissions Inventory
May 20, 2021: Facility submitted source test extension request.
June 23, 2021: DEQ responded to the facility's extension request.
July 14, 2021: Covanta submitted source test plan.
July 21, 2021: DEQ provided notes on source test plan.
Sept. 13, 2021: Covanta submitted revised Source Test Plan.
Oct. 22, 2021: DEQ requests revisions to the Source Test Plan.
Nov. 8, 2021: Covanta submitted revised Source Test Plan dated Nov. 5, 2021.
Nov. 24, 2021: Covanta submitted minor revisions to the test plan.
Dec. 3, 2021: DEQ approved source test plan.
Dec. 7-8, 2021: Covanta completes a portion of scheduled source testing.
Dec. 8, 2021: Covanta submits extension request for completion of remainder of source testing.
Dec. 14, 2021: DEQ response to Covanta extension request
Feb. 1, 2022: Covanta submits Source Test Reports from source testing completed in December 2021.
April 8, 2022: DEQ issued Source Test Review Reports for source testing completed in December 2021
May 9, 2022: Covanta submits Source Test Reports for source testing completed in March 2022
June 3, 2022: DEQ sends letter to Covanta requiring revisions to the Source Test Reports for source testing completed in March 2022
July 5, 2022: Covanta submits revised Source Test Reports for source testing completed in March 2022.
July 21, 2022: Covanta submits Source Test Plan for additional source testing
Aug. 16, 2022: DEQ requests revisions to the Source Test Plan
Aug. 19, 2022: DEQ issues Source Test Review Reports for source testing completed in March 2022 and sends letter requesting revisions to the Emissions Inventory
Aug. 24, 2022: Facility submitted Emissions Inventory extension request.
Aug. 26, 2022: DEQ responded to Emissions Inventory extension request.
Oct. 18, 2022: Facility submitted revised Emissions Inventory.
Mar. 20, 2023: DEQ responded to the Oct. 18, 2022 Emissions Inventory submittal with a request for revisions and additional information.
Apr. 17, 2023: Facility submitted Emissions Inventory extension request.
Apr. 25, 2023: DEQ responded to Emissions Inventory extension request.
May 12, 2023: Facility submitted revised Emissions Inventory.
July 28, 2023: DEQ responded to the May 12, 2023, Emissions Inventory submittal with a request for revisions and additional information.
Aug. 31, 2023: Facility submitted revised Emissions Inventory.
Oct. 18, 2023: DEQ requested additional information related to the Emissions Inventory.
Oct. 20, 2023: Facility submitted additional information related to the Emissions Inventory.
Nov. 7, 2023: DEQ issues approval letter for the Emissions Inventory.