The facility is a 650-megawatt natural gas-fired electric generating plant consisting of two units. Unit 1 is a base-load power plant consisting of a combustion turbine generator, one heat recovery steam generator, and one steam turbine. Unit 1 began commercial operation in June 2007. Unit 2 is a non-base-load power plant consisting of 12 reciprocating internal combustion engines. Unit 2 began commercial operation in December 2014.
Under Review/Operating. On July 12, 2019, the Department received a complete Request for Amendment 11 to the Port Westward Generating Project site certificate (RFA11). RFA11 seeks Council approval to add a 4 to 6 megawatt battery energy storage system to the existing facility, which would be constructed on an approximately 100 feet x 90 feet area within the existing site boundary. The certificate holder proposes to construct the battery energy storage system utilizing either lithium-ion battery or flow battery technology. The certificate holder also proposes several additional modifications to the site certificate that are not specific to the BESS, including administrative corrections to the facility description and modification of conditions related to spill containment, revegetation success criteria, wetland buffers, and wildlife.

The Department is reviewing the RFA under the Type A review process described under OAR 345-027-0351(2). The Department issued its draft proposed order on RFA11 on August 29, 2019, which is available below. A public comment period is now open. Additionally, EFSC will hold a public hearing on the draft proposed order and complete amendment request on September 26, 2019.

Public Hearing:
September 26, 2019, 5:00 p.m.
Clatskanie River Inn
600 E. Columbia River Highway
Clatskanie, Oregon 97106

Call-in: 1-877-873-8017
Passcode: 799345#

A written public comment period is now open on the complete RFA and the DPO. Written comments on the RFA and DPO must be received by the Oregon Department of Energy by the close of the September 26, 2019 public hearing, and must be submitted in writing by mail, email, hand-delivery, or fax to:

Christopher M. Clark, Siting Analyst
Oregon Department of Energy
550 Capitol Street NE, 1st Floor
Salem, OR 97301
Email: christopher.clark@oregon.gov​
Fax: 503-373-7806

Written and oral comments may be submitted at the public hearing. The EFSC will not accept comments on the RFA or the DPO after the close of the record of the September 26, 2019 DPO public hearing.
Columbia County, 4.5 miles north of Clatskanie. Online Map
Applicant/Certificate holder: Portland General Electric
ODOE contact: Chris Clark
Applicant/Certificate holder contact: Arya Behbehani
​​​​​​​​​​​

Project Amendment(s)

 ​
  
Description
  
Preliminary Request for Amendment 11
04/23/2019
07/12/2019
08/29/2019
08/29/2019
​​

Project Timeline

  
Additional Documents
  
06/21/2001
11/05/2001
11/08/2002
11/08/2002
11/12/2002
12/05/2003
12/16/2003
09/24/2004
10/13/2004
01/28/2005
01/31/2005
05/19/2006
07/11/2006
09/29/2006
10/02/2006
03/27/2009
04/14/2009
03/12/2010
03/12/2010
08/19/2011
09/28/2011
03/15/2013
03/21/2013
08/23/2013
08/28/2013
08/29/2019
​​​​
​​​​​​​​​​​​​​​​​​​​
​Contact the Facility Siting Team:
​​​​​​​​​​​​​​​
​​​​​​​​​​​​​​​​​​​​​​​​ ​​

Exhibit Files Reference

  • Exhibit A: Applicant Information 
  • Exhibit B: Project Description
  • Exhibit C: Property Location and Maps
  • Exhibit D: Organizational Information
  • Exhibit E​: Permits Required
  • Exhibit F: Property Ownership 
  • Exhibit G: Materials Analysis
  • Exhibit H: Geology and Soil Stability 
  • Exhibit I: Soils
  • Exhibit J: Wetlands
  • Exhibit K: Land Use
  • Exhibit L: Protected Areas
  • Exhibit M: Financial Analysis
  • Exhibit N​: Non-generating Facility Information
  • Exhibit O: Water Requirements
  • Exhibit P: Fish Wildlife Habitat 
  • Exhibit Q: Threatened and Endangered Plants and Animals
  • Exhibit R: Scenic Aesthetic Values 
  • Exhibit S: Cultural Resources
  • Exhibit T: Recreational Facilities 
  • Exhibit U: Public Services
  • Exhibit V​: Waste Minimization 
  • Exhibit W: Site Restoration
  • Exhibit X: Noise 
  • Exhibit Y: Carbon Dioxide Emissions 
  • Exhibit Z: Cooling Towers  
  • Exhibit AA: EMFs – Electric and Magnetic Fields
  • Exhibit BB: Other Information
  • Exhibit CC: Additional Statutes Rules Ordinances
  • Exhibit DD​: Other Specific Standards